eStruxture CAL-3 Rocky View

Calgary metropolitan area, Alberta, CanadaUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

eStruxture's current Calgary operator page, checked October 28, 2026, states that CAL-3's first phase is sold out. This is a leasing statement, not confirmation that the first phase is operating or that the facility has opened. eStruxture's CAL-3 facility is under construction in Rocky View County with 90 MW of total power and CoreWeave anchoring an undisclosed portion of Phase 1. Opening remains targeted for fall 2026.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Phase 1Under construction

CoreWeave allocation is undisclosed and must not be inferred from the 90 MW facility total.

Remaining CAL-3 capacityAnnounced or preconstruction

Balance of the 90 MW total-power facility after the undisclosed Phase 1 allocation; not delivered or committed by default.

Milestones (4)
Government register places project in 2024-2026 construction window

2024 · Recorded actual event

Completed · Construction started

Source not linked
CAL-3 announced

Nov 15, 2024 · Recorded actual event

Completed · Announced

Source not linked
CoreWeave announced for a portion of Phase 1

May 14, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
CAL-3 target opening

2026 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

eStruxture Data Centers

Operator

Sources by role
Operator (1)
Operator (1)
Other participants (4)
Calgary Economic Development

Government authority

Sources by role
Government authority (1)
Government of Alberta

Government authority

Sources by role
Government authority (1)
Government authority (1)
Invest Alberta

Government authority

Sources by role
Government authority (1)
Rocky View County

Government authority

Sources by role
Government authority (1)
Government authority (1)

Site & development

Representative data hall area

Source report

8,625 square feet approximately

Source

Technical specifications

Facility total power

Source report

90 MW total power

Source

Additional project facts

Status

Actual

Construction

Source

Target opening

Source report

Fall / H2 2026

Source

Tier design

Actual

Tier III-designed

Source

Anchor tenant

Actual

CoreWeave

Source

Anchor tenant scope

Actual

Portion of Phase 1

Source

Latitude

Source report

51.21 decimal degrees

Source

Longitude

Source report

-113.91 decimal degrees

Source

Carrier neutral

Source report

True

Source

Capacity boundary decision

Actual

90 MW facility total power; CoreWeave portion of Phase 1 undisclosed; no operating capacity claimed

Source

Infrastructure & permits

Technical details (3)
Electric grid

Under construction

90 MW total power

Facility design/total power; government generation wording is not accepted as onsite generation evidence.

Cooling system

Under construction

125 kW+ per cabinet

Maximum cabinet-density design with liquid-cooling support.

Fiber

Planned or represented

Planned network/interconnection with CAL-1 and CAL-2; implementation status not publicly disclosed.

Project map

Project map

1 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
2
Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Beacon Indus AI Data Center Hub

Preconstruction · About 3.2 km east of Calgary and 2.4 km northwest of Indus, Alberta, Canada

Shared participant: Rocky View County · Same market: Alberta, Canada