The Alberta Utilities Commission's current Indus project page, checked October 28, 2026, confirms that the oral hearing has been held and the power-plant application remains under consideration; this is not an approval decision. Beacon's Indus hub has an approved municipal planning envelope while its proposed 1,494 MWe on-site gas plant remains before the Alberta Utilities Commission. About 1,200 MWe would supply co-located data halls; IT load is unknown.
Capacity
Proposed generation capability
Proposal1,494 MW
Indus on-site thermal power plant · Phase
Phase scope; not a whole-site figure
SourceProposed power supplied to data halls
Planned / design or future potential1,200 MW
Future co-located data halls · Phase
Phase scope; not a whole-site figure
SourceReciprocating generation
Proposal460 MW
Indus on-site thermal power plant · Phase
Phase scope; not a whole-site figure
SourceCombined cycle generation
Proposal1,034 MW
Indus on-site thermal power plant · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
North, central and south development cells; individual development permits still required.
About 1,200 MWe is proposed supply to halls, not IT load.
Proposed 1,494 MWe generation; hearing scheduled after cutoff.
No capacity, approval or construction milestone established.
Milestones (4)
Jun 17, 2025 · Recorded actual event
Completed · Permit approved
Source not linkedJan 19, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedMar 9, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedAug 18, 2026 · Forecast / planned record
Forecast · Permit filed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Primary
Developer (1)
- Campuses · Corroborating
Developer
Sources by role
Developer (1)
- Notice of Early Decision with Reasons — Beacon AI Centers Indus Project · Mar 10, 2026 · Corroborating
Developer (1)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Primary
Investor
Sources by role
Investor (1)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Primary
Other participants (6)
Government authority
Sources by role
Government authority (1)
Government authority (1)
- Beacon AI Hub — Thermal Power Plant Application · Corroborating
Government authority
Sources by role
Government authority (1)
- Notice of Early Decision with Reasons — Beacon AI Centers Indus Project · Mar 10, 2026 · Primary
Government authority (1)
- Public notice — Beacon AI Centers Indus Project · Jan 6, 2026 · Corroborating
Supplier
Sources by role
Supplier (1)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Beacon AI Hub Area Structure Plan — Bylaw C-8638-2025 · Jun 17, 2025 · Corroborating
Government authority (1)
- Council Decisions: June 17, 2025 · Jun 17, 2025 · Corroborating
Government authority (1)
Supplier
Sources by role
Supplier (1)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Primary
Contractor
Sources by role
Contractor (1)
- Beacon AI Hub Area Structure Plan — Bylaw C-8638-2025 · Jun 17, 2025 · Primary
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Planned or represented
1,494 MWe generation
onsite natural gas generation — 1494 MWe_generation; AUC application under review.
Planned or represented
1,200 MWe supply to halls
data hall power supply — 1200 MWe_supply_to_halls; proposed normal operating scenario.
Potential or planned
natural gas pipeline; options under evaluation.
Potential or planned
1,500 m3 per day estimate
water supply — 1500 m3_per_day_estimate; source and approvals open.
Planned or represented
solar agrivoltaics; approved planning concept; project not permitted.
Project map
Project map
1 of 1 project point mappedBuilding · Issued
Beacon AI Hub Area Structure Plan
Rocky View County
Jun 17, 2025
Sources (2)
- Beacon AI Hub Area Structure Plan — Bylaw C-8638-2025 · Jun 17, 2025 · Primary
- Council Decisions: June 17, 2025 · Jun 17, 2025 · Corroborating
Other · Under review
Beacon AI Centers — Indus Project Thermal Power Plant
Alberta Utilities Commission
Jan 19, 2026
Sources (3)
- Indus AI Data Center Hub FAQs · Feb 1, 2026 · Corroborating
- Beacon AI Centers — Indus Project Thermal Power Plant · Primary
- Beacon AI Hub — Thermal Power Plant Application · Corroborating
Other · Documented
Beacon AI Centers Indus Project
Impact Assessment Agency of Canada
Mar 9, 2026
Sources (2)
- Notice of Early Decision with Reasons — Beacon AI Centers Indus Project · Mar 10, 2026 · Primary
- Public notice — Beacon AI Centers Indus Project · Jan 6, 2026 · Corroborating
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Under construction · Calgary metropolitan area, Alberta, Canada
Shared participant: Rocky View County · Same market: Alberta, Canada
Compare in a collection