Skip to content
All records
Property and infrastructure intelligenceSite record

CyrusOne Freestone County Data Center Campus

Fairfield / Freestone Energy Center, Texas, United StatesUnder constructionDiligence evidence / compare baseline
Capacity
380 MW
Utility capacity
Lead participant
CyrusOne
Developer
Last updated
Sep 13, 2026
Most recent public record update

About CyrusOne Freestone County Data Center Campus

CyrusOne is developing a multiphase data center campus beside Calpine's Freestone Energy Center near Fairfield, Texas. The first phase is supported by a 380 MW agreement for power, grid connectivity and site infrastructure, and Calpine has an exclusive agreement for an additional 380 MW Phase 2. Both figures describe contracted supply and supporting infrastructure rather than data center IT load. CyrusOne says the campus will combine grid and onsite generation, use closed-loop cooling and represent more than $500 million of capital investment across phases. Texas records identify C1 Freestone 1 LLC as owner of registered data center fit-outs and Paile LLC as occupant/operator of record; the ultimate compute customer remains undisclosed.

Projects sharing a market, utility, or organization.

4 related

Capacity

Utility capacity
Operating capacityNo reviewed operating IT-capacity value is included in this record.

No additional capacity claims are published.

Development

2 phases · 4 milestones
Freestone Phase 1Under Construction

Initial campus phase supported by a 380 MW power/grid/site-infrastructure agreement; the figure is supply infrastructure, not IT load.

Freestone Phase 2Planned

Second phase has an exclusive additional 380 MW power/grid/site-infrastructure agreement.

Feb 9, 2026
Calpine and CyrusOne announced 380 MW Phase 1 infrastructure agreement
Completed
Mar 24, 2026
Freestone Data Center appears on Texas Comptroller certified list
Completed
Jun 1, 2026
CyrusOne broke ground on Freestone campus in June 2026
Completed
Aug 4, 2026
Texas accessibility project registrations filed for data center fit-outs
Completed

Infrastructure

Electric GridSecured Or Contracted

380 MW

Phase 1 agreement supplies access to power, grid connectivity and site infrastructure; this is not IT load.

Electric GridSecured Or Contracted

380 MW

Separate Phase 2 additional 380 MW agreement; the figure is not IT load.

Onsite GenerationPlanned Or Represented

CyrusOne states the multiphase campus will use both grid and onsite generation; onsite-generation MW is undisclosed.

Closed Loop CoolingPlanned Or Represented

Closed-loop cooling is planned to minimize ongoing water use; thermal capacity is undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
4
Mapped records
0
Capacity figures
2

No map point available

Power & interconnection: 2Generation & storage: 1Cooling & water: 1

Facts & sources

Claim review and source dates are shown separately. A record update date is not a claim review date.

7 facts
Phase1 Power Grid Agreement
380 MW
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158754
Phase2 Power Grid Agreement
380 MW
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158755
Multiphase Capital Investment Minimum
$500,000,000
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158756
Fitout A Area
306,216 sq. ft.
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158757
Fitout C Area
306,216 sq. ft.
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158758
Fitout A Estimated Cost
$100,000,000
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158759
Fitout C Estimated Cost
$100,000,000
actual
Claim review
Approved
Claim date
Physical subject
CyrusOne Freestone County Data Center Campus · Project
Claim reference
158760