CyrusOne DFW3–DFW5 Allen Data Center Campus
- Planned critical IT
- 77 MW
- Updated
- Oct 28, 2026
CyrusOne DFW3–DFW5 Allen Data Center Campus, also known as CyrusOne Allen Campus, is a partially operational data center campus in Allen, TX, US associated with CyrusOne. More than 90 acres; DFW3–DFW5; 976,000 square feet at full build; 50 MW total IT capacity. Large North Texas campus with water-free cooling, renewable electricity and multilayer physical security. Available incentive or entitlement information remains subject to the applicable agreement terms and performance conditions.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
77 MW is the operator-published facility or campus design boundary.
50 MW is the operator-published facility or campus IT design boundary.
Milestones (1)
Jan 1, 2025 · Recorded actual event
Completed · Status changed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- CyrusOne CyrusOne DFW3–DFW5 profile · Aug 28, 2026 · Primary
Site & development
Additional project facts
Capacity basis
ActualCyrusOne publishes 77 MW of critical IT capacity for this record boundary.
SourceInfrastructure & permits
Technical details (4)
Energized
Purpose-built high-efficiency campus with water-free cooling, renewable-power sourcing and multilayer physical security.
Operational
CyrusOne describes closed-loop or air-cooled systems; the profile does not infer facility water use beyond the cited site specification.
Energized
Large North Texas campus with water-free cooling, renewable electricity and multilayer physical security.
Operational
Cooling and efficiency claims remain limited to source-defined designs; no delivered load or water use is inferred.
Project map
Building · Issued
CyrusOne Allen
City of Allen
Jan 31, 2024
Sources (1)
- CyrusOne sustainability reporting · Aug 30, 2026 · Primary
Other · Issued
CyrusOne Allen DFW3–DFW5 campus
City of Allen
Jan 1, 2025
Sources (1)
- CyrusOne Allen campus site plan · Jan 1, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (4)
Partially operational · Austin, Texas, United States
Shared participant: CyrusOne · Same market: Texas, United States
Compare in a collectionUnder construction · Whitney / Clifton, Texas, United States
Shared participant: CyrusOne · Same market: Texas, United States
Compare in a collectionPartially operational · Carrollton, Texas, United States
Shared participant: CyrusOne · Same market: Texas, United States
Compare in a collectionPartially operational · Lewisville, Texas, United States
Shared participant: CyrusOne · Same market: Texas, United States
Compare in a collection