Cipher McLennan AI Data Center Campus

Texas, United StatesPreconstruction
Capacity
500 MW
Planned / design
Lead participant
Cipher Digital
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Cipher McLennan AI Data Center Campus

Cipher is advancing McLennan as a 500 MW gross-power HPC development site. The site is secured and in the interconnection process, but it is not yet an operating data center. Cipher Digital is publicly identified in the project record for McLennan County, TX, US. The disclosed development record includes 500 MW gross pipeline capacity; land secured; deposits funded; 2028 target subject to ERCOT. Power and infrastructure include planned hyperscale campus and ERCOT interconnection. Cipher reports 500 MW of gross pipeline capacity subject to ERCOT.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential500 MWDesign · Cipher McLennan AI Data Center Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Project-wide phase for Cipher McLennan AI Data Center Campus; capacity remains classified as future potential.

Aug 10, 2026
McLennan project status and capacity disclosed
Completed
Land secured and grid studies submitted
Forecast

Infrastructure

Electric GridPlanned Or Represented

500 MW

Cipher reports 500 MW of gross pipeline capacity subject to ERCOT.

Site FacilityPlanned Or Represented

Planned hyperscale campus and ERCOT interconnection.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
McLennan campus | McLennan County | Texas
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
500 MW
Design
Capacity Basis
Cipher reports 500 MW of gross pipeline capacity subject to ERCOT.
Actual
Development Scale
500 MW gross pipeline capacity
Actual
Development Milestone
Land secured
Actual
Power Arrangement
Deposits funded
Actual
Site Configuration
2028 Target subject to ERCOT.
Actual