Cartis diligence evidence schedule
AWS PDX-154 Boardman Airport Campus
PRJ-0124 · Site · East of Boardman Airport, Oregon, United States
Record last updated Oct 28, 2026
Scope and capacity
PDX-154 is an approved four-building campus planned near Boardman Airport, with land-use conditions addressing water, wastewater and airport impacts. AWS PDX-154 Boardman Airport Campus is in East of Boardman Airport, OR, US and is a data center campus with preconstruction status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (5)
Land use approval date · 2026-03-31
Actual · AWS PDX-154 Boardman Airport Campus (Project)
Claim 13812 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon plans another data center southwest of Tri-Cities
Tri-Cities Area Journal of Business · Document date: Apr 14, 2026 · Primary
Source reference: SRC-0838 · News report · Recorded authority: Secondary
Source URL
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
- Amazon purchases 1,300 acres in Morrow County, Oregon
Data Center Dynamics · Document date: Mar 31, 2026 · Corroborating
Source reference: SRC-0839 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/amazon-purchases-1300-acres-in-morrow-county-oregon/
https://www.datacenterdynamics.com/en/news/amazon-purchases-1300-acres-in-morrow-county-oregon/
- Morrow County Board Minutes — CREZ III agreements
Morrow County · Document date: May 3, 2023 · Corroborating
Source reference: SRC-0837 · Government record · Recorded authority: Official primary
Source URL
https://www.morrowcountyor.gov/sites/default/files/fileattachments/board_of_commissioners/meeting/16590/5-3-23_board_minutes.pdf
https://www.morrowcountyor.gov/sites/default/files/fileattachments/board_of_commissioners/meeting/16590/5-3-23_board_minutes.pdf
- AWS Investment — Eastern Oregon
Amazon Web Services · Document date: Jan 1, 2022 · Corroborating
Source reference: SRC-0831 · Company announcement · Recorded authority: Party primary
Source URL
https://assets.aboutamazon.com/fc/65/e3944125451698e1de8d734e2ac7/easternoregon-eis-factsheet-2022.pdf
https://assets.aboutamazon.com/fc/65/e3944125451698e1de8d734e2ac7/easternoregon-eis-factsheet-2022.pdf
Planned building count · 4 data center buildings
Actual · Four-building campus (Phase)
Claim 13813 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon plans another data center southwest of Tri-Cities
Tri-Cities Area Journal of Business · Document date: Apr 14, 2026 · Primary
Source reference: SRC-0838 · News report · Recorded authority: Secondary
Source URL
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
Planned floor area · 816,000 sq. ft.
Reported rounded · Four-building campus (Phase)
Claim 13814 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Amazon plans another data center southwest of Tri-Cities
Tri-Cities Area Journal of Business · Document date: Apr 14, 2026 · Primary
Source reference: SRC-0838 · News report · Recorded authority: Secondary
Source URL
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
Stormwater evaporation pond area · 8 acres
Actual · AWS PDX-154 Boardman Airport Campus (Project)
Claim 13815 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon plans another data center southwest of Tri-Cities
Tri-Cities Area Journal of Business · Document date: Apr 14, 2026 · Primary
Source reference: SRC-0838 · News report · Recorded authority: Secondary
Source URL
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
Wastewater pond count · 2 ponds
Actual · AWS PDX-154 Boardman Airport Campus (Project)
Claim 13816 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon plans another data center southwest of Tri-Cities
Tri-Cities Area Journal of Business · Document date: Apr 14, 2026 · Primary
Source reference: SRC-0838 · News report · Recorded authority: Secondary
Source URL
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
https://www.tricitiesbusinessnews.com/articles/amazon-plans-another-data-center-southwest-of-tri-cities
Counterparties and capital
Amazon Data Services, Inc. · Developer · CMP-0451
Amazon Web Services · Owner · CMP-0152
City of Boardman · Government authority · CMP-0454
Morrow County · Government authority · CMP-0452
Port of Morrow · Government authority · CMP-0455
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.