AVAIO Digital Project Leo
About AVAIO Digital Project Leo
Project Leo is AVAIO Digital's 760-acre, multi-building AI-ready campus in Little Rock, with construction underway and first occupancy targeted for June 2027.
Capacity
No additional capacity claims are published.
Development
4 phases · 1 milestonesFirst campus phase; $6B combined investment estimate includes infrastructure, power and tenant deployments.
Power-supply phase, not IT load; exact plant configuration and permits undisclosed.
Would raise planned grid supply from 150 MW to 570 MW; not an IT-capacity assertion.
On-site solar is a generation resource rather than IT capacity or baseload.
Infrastructure
420 MW
Additional grid power planned for 2030; would bring grid plan to 570 MW.
500 MW generation
On-site generation plan supplied via direct NGPL access; not IT load. Numeric capacity is a disclosed lower bound; the plus qualifier is retained here and must not be treated as an exact value.
75 MW
Planned on-site solar; no delivery date disclosed. Numeric capacity is a disclosed lower bound; the plus qualifier is retained here and must not be treated as an exact value.