Cartis diligence evidence schedule
AVAIO Digital Project Leo
PRJ-0535 · Site · 145th Street, Little Rock, Arkansas, United States
Record last updated Oct 28, 2026
Scope and capacity
AVAIO’s current Little Rock project page forecasts initial grid power in the fourth quarter of 2027, while its homepage gives the third quarter of 2027. These differing current forecasts supersede treating the earlier June 2027 target as settled; grid availability is not a data-center opening or full-capacity commissioning. Project Leo is AVAIO Digital's 760-acre, multi-building AI-ready campus in Little Rock, with construction underway; an earlier record targeted first occupancy for June 2027, before the later power-delivery forecasts noted above.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (1)
Project identity · AVAIO Digital Project Leo
Source report · AVAIO Digital Project Leo (Project)
Claim 132378 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Little Rock, Arkansas — Project Leo
AVAIO Digital · Document date: Not stated · Primary
Source reference: SRC-7082 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.avaiodigital.com/developments/little-rock-arkansas
https://www.avaiodigital.com/developments/little-rock-arkansas
- AVAIO Digital announces new large-scale AI-ready data center and power campus in Little Rock, Arkansas
AVAIO Digital · Document date: Jan 12, 2026 · Primary
Source reference: SRC-7083 · Company announcement · Recorded authority: Party primary
Source URL
https://www.avaiodigital.com/updates/avaio-digital-announces-new-large-scale-ai-ready-data-center-and-power-campus-in-little-rock-arkansas
https://www.avaiodigital.com/updates/avaio-digital-announces-new-large-scale-ai-ready-data-center-and-power-campus-in-little-rock-arkansas
Counterparties and capital
Entergy Arkansas · Utility provider · CMP-1260
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.