Cartis diligence evidence schedule

Yondr London Campus Building 1

PRJ-1027 · Site · Slough, England, United Kingdom

Record last updated Oct 28, 2026

Scope and capacity

Yondr London Campus Building 1 is a separately tracked building within Yondr’s Wexham Road campus. The three-building program totals just over 100 MW: 30 MW Building 1, 30 MW Building 2 and 40 MW Building 3. Shared-campus permits and infrastructure do not turn the combined total into this building’s capacity. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Headline: 30 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Yondr Slough Building 1 | Slough | England | GB

Actual · Yondr London Campus Building 1 (Project)

Claim 68055 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Lifecycle status · Operating

Actual · Yondr London Campus Building 1 (Project)

Claim 68056 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Reported capacity · 30 MW

Design · Yondr London Campus Building 1 (Project)

Claim 68057 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Capacity basis · Yondr publishes 30 MW for the completed first London campus building.

Actual · Yondr London Campus Building 1 (Project)

Claim 68058 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Location context · Yondr Slough Building 1 | Slough | England | GB

Actual · Yondr London Campus Building 1 (Project)

Claim 80965 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Lifecycle status · Operating

Actual · Yondr London Campus Building 1 (Project)

Claim 80966 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Reported capacity · 30 MW

Design · Yondr London Campus Building 1 (Project)

Claim 80967 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Capacity basis · 30 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Yondr London Campus Building 1 (Project)

Claim 80968 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Operator confirmed · Yondr Group

Actual · Yondr London Campus Building 1 (Project)

Claim 80969 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Facility capacity basis · 30 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Yondr London Campus Building 1 (Project)

Claim 80970 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Current lifecycle · Operating

Actual · Yondr London Campus Building 1 (Project)

Claim 80971 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 1 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3878 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Counterparties and capital

Yondr Group · Developer · CMP-1426

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.