Yondr Dallas Lancaster Data Center Campus
- Planned critical IT
- 550 MW
- Updated
- Oct 28, 2026
Yondr’s Lancaster campus spans 163 acres and is planned as a multi-building hyperscale development. A city agreement sets minimum first-phase building, investment and employment commitments, while Yondr’s current specification distinguishes the initial 150 MVA utility allocation from a 500 MW+ IT full-build target. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Yondr’s Lancaster campus spans 163 acres and is planned as a multi-building hyperscale development. A city agreement sets minimum first-phase building, investment and employment commitments, while Yondr’s current specification distinguishes the initial 150 MVA utility allocation from a 500 MW+ IT full-build target. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.
Milestones (2)
Apr 14, 2025 · Recorded actual event
Completed · Permit approved
Source not linkedDec 2028 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Yondr Dallas Lancaster Data Center Campus official profile · Aug 28, 2026 · Primary
Capital & incentives
Capital claims
Site & development
Additional project facts
Capacity basis
ActualCurrent first party material says 500 MW+ of IT capacity; the earlier 550 MW announcement is retained as historical context.
SourceFacility capacity basis
ActualCurrent first party material says 500 MW+ of IT capacity; the earlier 550 MW announcement is retained as historical context.
SourceInfrastructure & permits
Technical details (3)
Planned or represented
500 MW
Published IT design boundary; utility service and operating load remain distinct.
Planned or represented
Carrier-neutral or resilient fibre connectivity described for the individual facility.
Secured or contracted
150 MVA
Initial permanent allocation targeted for December 2028; full site total is 828 MVA.
Project map
Other · Issued
Yondr Dallas campus
City of Lancaster
Apr 14, 2025
Sources (1)
- Lancaster–Redwood Dallas development agreement · Apr 14, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.