Yandex Vladimir AI Data Center

PRJ-1225 · Site · Vladimir, VLA, Russia

Record last updated Oct 28, 2026

Scope and capacity

Yandex is building a new data center near its existing Vladimir facility to expand the Yandex Cloud availability zone. The project is designed for more than 40 MW, with direct high-voltage utility connection, modular free cooling and a 25.6 Tbps link to the existing site. Yandex plans to bring the new facility into the availability zone in 2026.

Headline: More than 40 MW Facility design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Reported capacity · More than 40 MW planned facility design capacity

Facility electrical / design capacity · Yandex Vladimir AI Data Center (Project)

Claim 156653 · Recorded claim type: Forecast · Review: Approved · Claim date: Sep 24, 2025

Headline treatment: Selected headline

  1. Yandex data-center infrastructure

    Yandex · Document date: Sep 1, 2026 · Corroborating

    Source reference: SRC-7655 · Company announcement · Recorded authority: Party primary

    Source URL

    https://infra.yandex.ru/datacenters

  2. Yandex to build new Vladimir data center

    Yandex · Document date: Sep 24, 2025 · Primary

    Source reference: SRC-7654 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.yandex.ru/press-releases?id=24-09-2025-05&year=2025

Counterparties and capital

Yandex · Operator · CMP-1684

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.