Scope and capacity
On September 24, 2026, VIRTUS announced completion of a £2.45 billion platform financing package that explicitly supports future LONDON19 investment. The financing is shared across the platform and is not LONDON19’s individual project cost or evidence of opening. VIRTUS LONDON19 is a planned data-center facility within the Slough Trading Estate and the wider VIRTUS Slough campus. VIRTUS announced the project in June 2026 with 32.5 MW of IT load and said planning permission had already been secured through the estate’s Simplified Planning Zone, with SEGRO to develop the powered shell. The current VIRTUS Slough campus page later lists LONDON19 at 33.5 MW and 8,500 NTM, creating a material conflict between two first-party capacity figures. Planned features include advanced cooling, sustainable construction and provision for future waste-heat export.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (5)
Reported IT capacity · 32.5 MW
Design · VIRTUS LONDON19 Slough (Project)
Claim 158150 · Recorded claim type: Design · Review: Approved with conflict · Claim date: Not stated
Headline treatment: Conflicting source claims
Conflicting public evidence is preserved.
- VIRTUS Announces Expansion with the Addition of LONDON19
VIRTUS Data Centres · Document date: Jun 30, 2026 · Primary
Source reference: SRC-7919 · Company announcement · Recorded authority: Party primary
Source URL
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
Reported IT capacity · 33.5 MW
Design · VIRTUS LONDON19 Slough (Project)
Claim 158151 · Recorded claim type: Design · Review: Approved with conflict · Claim date: Not stated
Headline treatment: Conflicting source claims
Conflicting public evidence is preserved.
- Slough Data Centre Campus
VIRTUS Data Centres · Document date: Not stated · Primary
Source reference: SRC-7920 · Fact sheet · Recorded authority: Party primary
Source URL
https://virtusdatacentres.com/locations/uk/london/slough-campus
https://virtusdatacentres.com/locations/uk/london/slough-campus
Net technical space · 8,500 square meters
Design · VIRTUS LONDON19 Slough (Project)
Claim 158152 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Slough Data Centre Campus
VIRTUS Data Centres · Document date: Not stated · Primary
Source reference: SRC-7920 · Fact sheet · Recorded authority: Party primary
Source URL
https://virtusdatacentres.com/locations/uk/london/slough-campus
https://virtusdatacentres.com/locations/uk/london/slough-campus
Planning permission status · Secured
Actual · VIRTUS LONDON19 Slough (Project)
Claim 158153 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- VIRTUS Announces Expansion with the Addition of LONDON19
VIRTUS Data Centres · Document date: Jun 30, 2026 · Primary
Source reference: SRC-7919 · Company announcement · Recorded authority: Party primary
Source URL
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
Breeam target · Excellent
Forecast · VIRTUS LONDON19 Slough (Project)
Claim 158154 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- VIRTUS Announces Expansion with the Addition of LONDON19
VIRTUS Data Centres · Document date: Jun 30, 2026 · Primary
Source reference: SRC-7919 · Company announcement · Recorded authority: Party primary
Source URL
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
https://virtusdatacentres.com/press-releases/virtus-announces-expansion-with-the-addition-of-london19
Counterparties and capital
SEGRO plc · Developer · CMP-1701
VIRTUS Data Centres · Developer · CMP-1121