Cartis diligence evidence schedule
Verne Ile-de-France AI Campus
PRJ-0387 · Site · Ile-de-France, Île-de-France, France
Captured 2026-09-06T04:14:00.805Z · Record last updated 2026-08-25
SHA-256: 26684587f706780bfdd775307a203daa7bf4d588539d96388e08226d81174f9a
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Ardian and Verne plan a low-carbon AI and HPC campus in Ile-de-France with a 500 MW target and an initial approximately 200+ MW phase by 2030. Verne Ile-de-France AI Campus is located in Ile-de-France, FR and is a data center campus in preconstruction status.
Headline: 500 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Planned Initial Capacity Approximately Over · 200 MW
Planned / design or future potential · Verne Ile-de-France AI Campus (project)
Claim 35592 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france
Initial Phase Target Year · 2030
Planned / design or future potential · Verne Ile-de-France AI Campus (project)
Claim 35593 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france
Planned Total Capacity · 500 MW
Planned / design or future potential · Verne Ile-de-France AI Campus (project)
Claim 35594 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france - Major investment pledges at Choose France summit
Reuters · Document date: 2026-06-01 · Corroborating
https://www.reuters.com/business/retail-consumer/major-investment-pledges-choose-france-summit-2026-06-01/
Planned Investment Up To · €5 billion
Planned / design or future potential · Verne Ile-de-France AI Campus (project)
Claim 35595 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france - Major investment pledges at Choose France summit
Reuters · Document date: 2026-06-01 · Corroborating
https://www.reuters.com/business/retail-consumer/major-investment-pledges-choose-france-summit-2026-06-01/
Site In Large Industrial Hub · True
actual · Verne Ile-de-France AI Campus (project)
Claim 35599 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france
Low Carbon Electricity Design · True
actual · Verne Ile-de-France AI Campus (project)
Claim 35603 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france
Aion Bid Supporting Site · True
actual · Verne Ile-de-France AI Campus (project)
Claim 35604 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian, Artefact, Bull, EDF, Capgemini, iliad, Orange and Scaleway combine for AI Gigafactory bid
Capgemini · Document date: 2026-05-20 · Corroborating
https://www.capgemini.com/us-en/news/press-releases/ardian-artefact-bull-edf-capgemini-the-iliad-grouporange-and-scaleway-combine-their-expertise-to-run-as-acandidate-for-a-european-ai-gigafactory-in-france/
Hundreds Of Jobs Claimed · True
actual · Verne Ile-de-France AI Campus (project)
Claim 35605 · Review: Approved · Claim date: Not published
- Ardian and Verne announce digital infrastructure hub in Ile-de-France
Verne · Document date: 2026-06-01 · Primary
https://www.verne.co/news/news-at-choose-france-ardian-and-verne-announce-plans-for-a-digital-infrastructure-campus-in-%C3%AEle-de-france-to-strengthen-europes-industrial-and-ai-capacity - Ardian and Verne announce digital infrastructure hub in Ile-de-France
Ardian · Document date: 2026-06-01 · Corroborating
https://www.ardian.com/news-insights/press-releases/ardian-and-verne-announce-digital-infrastructure-hub-ile-de-france
Counterparties and capital
Ardian · Investor · CMP-0924
Bouygues Group · Contractor · CMP-0954
EDF · Utility Provider · CMP-0928
RTE · Utility Provider · CMP-0130
Verne · Developer, Operator · CMP-0923
€5,000,000,000 · 2026-06-01
Up-to amount for the physical campus; FT reported approximately one-third equity and two-thirds debt, with lenders undisclosed.
Ardian (Equity Sponsor) · Verne (Developer / Investment Vehicle)
Financing record 111; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.