Vantage VA4 Fredericksburg Data Center Campus
- Planned critical IT
- 192 MW
- Updated
- Oct 28, 2026
- Utility
- Dominion Energy Virginia
Vantage’s current VA4 page targets the first building to become operational in late 2027, with further phases through 2028. These are delivery forecasts for the phased campus, not evidence of current operation. Vantage VA4 Fredericksburg Data Center Campus, also known as Vantage VA4 Fredericksburg, is a data center project in Fredericksburg, VA, US associated with Vantage Data Centers. 82-acre campus; three planned two-story data centers; 929,000 square feet; 192 MW critical IT load. Dominion Energy-served campus with a private 270 MW onsite substation, liquid-cooling support and diverse fiber paths. 192 MW is the operator-published future facility or full-build design boundary.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
192 MW is the operator-published future facility or full-build design boundary. It is not operating IT load.
Milestones (2)
Nov 6, 2025 · Recorded actual event
Completed · Announced
Source not linkedMar 9, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Vantage Data Centers Vantage VA4 Fredericksburg profile · Aug 27, 2026 · Primary
Other participants (1)
Utility provider
Sources by role
Utility provider (1)
- Centreport 230 kV electric transmission project · Aug 29, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
$2bnNov 6, 2025
Vantage-announced VA4 development investment; not a financing close or facility valuation.
Parties & sources
Vantage Data Centers (Borrower)
Sources (1)
- Vantage announces $2 billion VA4 investment · Nov 6, 2025
Site & development
Additional project facts
Infrastructure & permits
Technical details (3)
Planned or represented
Dominion Energy-served campus with a private 270 MW onsite substation, liquid-cooling support and diverse fiber paths.
Planned or represented
Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.
Planned or represented
270 MW gross
Private onsite substation and Centreport 230 kV interconnection; gross electrical rating is not IT load.
Project map
Other · Under review
Vantage VA4 campus
Stafford County
Mar 9, 2026
Sources (1)
- Vantage VA4 easement dedication application 26157023 · Mar 9, 2026 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (4)
Proposed · Fredericksburg, Virginia, United States
Same locality: Fredericksburg
Compare in a collectionPartially operational · Ashburn, Virginia, United States
Shared participant: Dominion Energy Virginia · Same market: Virginia, United States
Compare in a collectionPartially operational · Sandston, Virginia, United States
Shared participant: Dominion Energy Virginia · Same market: Virginia, United States
Compare in a collectionPartially operational · Sterling, Virginia, United States
Shared participant: Vantage Data Centers · Same market: Virginia, United States
Compare in a collection