Cartis diligence evidence schedule

Vantage TPE11 Taipei

PRJ-0582 · Site · Taoyuan district / Taipei market, Taiwan

Record last updated Oct 28, 2026

Scope and capacity

Vantage opened TPE11 in Taoyuan on July 10, 2024. The five-story, carrier-neutral facility provides 16 MW of critical IT load and is supported by a dual-feed 161 kV on-site substation rated at 25 MVA.

Headline: 16 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Operating status · Operational

Actual · Vantage TPE11 Taipei (Project)

Claim 53233 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 10, 2024

  1. Vantage Data Centers' Growth Continued in 2024

    Vantage Data Centers · Document date: Jan 30, 2025 · Corroborating

    Source reference: SRC-2856 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-growth-continued-in-2024-driven-by-ai-and-cloud-adoption-secured-a-record-13-billion-in-incremental-funding/

  2. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Corroborating

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

  3. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Facility code · TPE11

Actual · Vantage TPE11 Taipei (Project)

Claim 53234 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 10, 2024

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Primary

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

  2. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: Mar 4, 2024 · Corroborating

    Source reference: SRC-2855 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

Critical IT load · 16 MW

Actual · Vantage TPE11 Taipei (Project)

Claim 53235 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 10, 2024

Headline treatment: Selected headline

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Corroborating

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

  3. CTCI project profile — Vantage TPE11 Data Center

    CTCI · Document date: Not stated · Corroborating

    Source reference: SRC-6693 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.ctci.com/www/ctci2022/page.aspx?C=1114&L=EN

Gross area · 215,000 square feet

Actual · Vantage TPE11 Taipei (Project)

Claim 53236 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: Mar 4, 2024 · Corroborating

    Source reference: SRC-2855 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Gross area metric · 20,000 square metres

Actual · Vantage TPE11 Taipei (Project)

Claim 53237 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: Mar 4, 2024 · Corroborating

    Source reference: SRC-2855 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Site area · 1 hectare

Actual · Vantage TPE11 Taipei (Project)

Claim 53238 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Primary

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

Building storeys · 5 storeys

Design · Vantage TPE11 Taipei (Project)

Claim 53239 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Corroborating

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Substation capacity · 25 MVA

Actual · Vantage TPE11 Taipei (Project)

Claim 53240 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Grid voltage · 161 kV

Actual · Vantage TPE11 Taipei (Project)

Claim 53241 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Power provider · Taiwan Power Company

Actual · Vantage TPE11 Taipei (Project)

Claim 53242 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: Jul 10, 2024 · Corroborating

    Source reference: SRC-2854 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Project loan · $64,000,000

Transaction scope · Vantage TPE11 Taipei (Project)

Claim 53243 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Mar 4, 2024

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: Mar 4, 2024 · Primary

    Source reference: SRC-2855 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

Cooling system · Closed loop chilled water using air cooled chillers

Actual · Vantage TPE11 Taipei (Project)

Claim 53244 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2853 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Counterparties and capital

Cathay United Bank · Lender · CMP-1353

CTBC Bank · Lender · CMP-1352

Taiwan Power Company · Utility provider · CMP-1351

Vantage Data Centers · Operator · CMP-0109

Investment commitment

$64,000,000 · Mar 4, 2024

Loan funds development of TPE11; not represented as total project cost.

Cathay United Bank (Lender) · CTBC Bank (Lender) · Vantage Data Centers (Sponsor)

Financing record 165; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.