Skip to content
← Return to profile

Cartis diligence evidence schedule

Vantage TPE11 Taipei

PRJ-0582 · Site · Taoyuan district / Taipei market, Taiwan

Captured 2026-09-06T04:13:37.361Z · Record last updated 2026-08-26

SHA-256: e1635cbae4f30344c13a3a439fa06f2f3da78564dc5b16e358fb77f4d78a81ff

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Vantage opened TPE11 in Taoyuan on July 10, 2024. The five-story, carrier-neutral facility provides 16 MW of critical IT load and is supported by a dual-feed 161 kV on-site substation rated at 25 MVA.

Headline: 16 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Operating Status · Operational

actual · Vantage TPE11 Taipei (project)

Claim 53233 · Review: Approved · Claim date: 2024-07-10T00:00:00+00:00

  1. Vantage Data Centers' Growth Continued in 2024

    Vantage Data Centers · Document date: 2025-01-30 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-growth-continued-in-2024-driven-by-ai-and-cloud-adoption-secured-a-record-13-billion-in-incremental-funding/
  2. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/
  3. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Facility Code · TPE11

actual · Vantage TPE11 Taipei (project)

Claim 53234 · Review: Approved · Claim date: 2024-07-10T00:00:00+00:00

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Primary

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/
  2. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: 2024-03-04 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

Critical It Load · 16 MW

actual · Vantage TPE11 Taipei (project)

Claim 53235 · Review: Approved · Claim date: 2024-07-10T00:00:00+00:00

Headline treatment: Selected headline

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/
  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/
  3. CTCI project profile — Vantage TPE11 Data Center

    CTCI · Document date: Not published · Corroborating

    https://www.ctci.com/www/ctci2022/page.aspx?C=1114&L=EN

Gross Area · 215,000 square feet

actual · Vantage TPE11 Taipei (project)

Claim 53236 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: 2024-03-04 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/
  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Gross Area Metric · 20,000 square metres

actual · Vantage TPE11 Taipei (project)

Claim 53237 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: 2024-03-04 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/
  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Site Area · 1 hectare

actual · Vantage TPE11 Taipei (project)

Claim 53238 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Primary

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/

Building Storeys · 5 storeys

design · Vantage TPE11 Taipei (project)

Claim 53239 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/
  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Substation Capacity · 25 MVA

actual · Vantage TPE11 Taipei (project)

Claim 53240 · Review: Approved · Claim date: Not published

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Grid Voltage · 161 kV

actual · Vantage TPE11 Taipei (project)

Claim 53241 · Review: Approved · Claim date: Not published

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Power Provider · Taiwan Power Company

actual · Vantage TPE11 Taipei (project)

Claim 53242 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Opens First Taipei Facility

    Vantage Data Centers · Document date: 2024-07-10 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-opens-first-taipei-facility/
  2. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Project Loan · $64,000,000

transaction scope · Vantage TPE11 Taipei (project)

Claim 53243 · Review: Approved · Claim date: 2024-03-04T00:00:00+00:00

  1. Vantage Data Centers Secures US$64M Loan from Top Taiwanese Banks

    Vantage Data Centers · Document date: 2024-03-04 · Primary

    https://vantage-dc.com/news/vantage-data-centers-secures-us64m-loan-from-top-taiwanese-banks-and-completes-taiwans-first-greenfield-hyperscale-data-center-project-financing-transaction/

Cooling System · Closed loop chilled water using air cooled chillers

actual · Vantage TPE11 Taipei (project)

Claim 53244 · Review: Approved · Claim date: Not published

  1. Taipei TPE1 Data Center

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/apac/taipei-taiwan/

Counterparties and capital

Cathay United Bank · Lender · CMP-1353

CTBC Bank · Lender · CMP-1352

Taiwan Power Company · Utility Provider · CMP-1351

Vantage Data Centers · Operator · CMP-0109

Investment Commitment

$64,000,000 · 2024-03-04

Loan funds development of TPE11; not represented as total project cost.

Cathay United Bank (Lender) · CTBC Bank (Lender) · Vantage Data Centers (Sponsor)

Financing record 165; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.