Vantage TPE11 Taipei

Taoyuan district / Taipei market, TaiwanOperating
Evidence
Planned critical IT
16 MW
Updated
Oct 28, 2026
Utility
Taiwan Power Company

Vantage opened TPE11 in Taoyuan on July 10, 2024. The five-story, carrier-neutral facility provides 16 MW of critical IT load and is supported by a dual-feed 161 kV on-site substation rated at 25 MVA.

Capacity

Critical IT load

Actual

16 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

TPE11 facilityOperational

1 building

Single five-story building.

Milestones (3)
Vantage announces TPE11

Dec 6, 2023 · Recorded actual event

Completed · Announced

Source not linked
US$64M TPE11 loan announced

Mar 4, 2024 · Recorded actual event

Completed · Financing

Source not linked
TPE11 opens

Jul 10, 2024 · Recorded actual event

Completed · Commercial operation

Source not linked

Participants

Vantage Data Centers

Operator

Sources by role
Operator (1)
Operator (1)
Other participants (3)
Cathay United Bank

Lender

Sources by role
CTBC Bank

Lender

Sources by role
Taiwan Power Company

Utility provider

Sources by role
Utility provider (1)
Utility provider (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Project loan

Transaction scope

$64,000,000

Source

Financing records

Investment commitment

$64m

Mar 4, 2024

Loan funds development of TPE11; not represented as total project cost.

Parties & sources

Cathay United Bank (Lender) · CTBC Bank (Lender) · Vantage Data Centers (Sponsor)

Site & development

Gross area

Actual

215,000 square feet

Source

Gross area metric

Actual

20,000 square metres

Source

Site area

Actual

1 hectare

Source

Building storeys

Design

5 storeys

Source

Technical specifications

Grid voltage

Actual

161 kV

Source

Power provider

Actual

Taiwan Power Company

Source

Cooling system

Actual

Closed loop chilled water using air cooled chillers

Source

Additional project facts

Operating status

Actual

Operational

Source

Facility code

Actual

TPE11

Source

Substation capacity

Actual

25 MVA

Source

Infrastructure & permits

Technical details (4)
Electric grid

Operational

16 MW IT

Current facility capacity.

Electric grid

Operational

25 MVA

Dual-feed 161 kV substation; not IT load.

Electric grid

Operational

161 kV

On-site dual-feed connection.

Cooling system

Operational

Closed-loop chilled water generated through air-cooled chillers; near-zero WUE claim.

Public-source research. Plans may change. See Evidence for sources and qualifications.