Cartis diligence evidence schedule

Vantage QC2 Quebec City Data Center Campus

PRJ-0822 · Site · Quebec City, Quebec, Canada

Record last updated Oct 28, 2026

Scope and capacity

Vantage QC2 Quebec City Data Center Campus, also known as Vantage QC2 Quebec City, is a data center project in Quebec City, QC, CA associated with Vantage Data Centers. 30-acre campus; four data centers at full development; 925,000 square feet; 86 MW combined critical IT capacity. Hydro-Quebec-powered campus using extensive free-air economization, redundant mechanical systems and carrier-neutral connectivity.

Headline: 86 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (13)

Location context · Vantage QC2 Quebec City | Quebec City | QC | CA

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 61835 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Lifecycle status · Partially operational

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 61836 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Reported capacity · 86 MW

Design · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 61837 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Capacity basis · Vantage Data Centers publishes 86 MW of critical IT capacity for this record boundary.

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 61838 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Location context · Vantage QC2 Quebec City | Quebec City | QC | CA

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97066 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Lifecycle status · Partially operational

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97067 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Reported capacity · 86 MW

Planned / design or future potential · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97068 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Capacity basis · 86 MW facility or campus design capacity.

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97069 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Data Centers Vantage QC2 Quebec City profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3432 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/north-america/quebec-city-canada/

Project boundary · Vantage QC2 Quebec City

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97071 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hydro-Québec data-center service

    Hydro-Québec · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5316 · Government record · Recorded authority: Official primary

    Source URL

    https://www.hydroquebec.com/data-center/

Location context · Quebec City, QC, CA

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97072 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hydro-Québec data-center service

    Hydro-Québec · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5316 · Government record · Recorded authority: Official primary

    Source URL

    https://www.hydroquebec.com/data-center/

Lifecycle status · Partially operational

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97073 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hydro-Québec data-center service

    Hydro-Québec · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5316 · Government record · Recorded authority: Official primary

    Source URL

    https://www.hydroquebec.com/data-center/

Development detail · 30-Acre campus; four data centers at full development; 925,000 square feet; 86 MW combined critical IT capacity.

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97074 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hydro-Québec data-center service

    Hydro-Québec · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5316 · Government record · Recorded authority: Official primary

    Source URL

    https://www.hydroquebec.com/data-center/

Capacity basis · 86 MW facility or campus design capacity.

Actual · Vantage QC2 Quebec City Data Center Campus (Project)

Claim 97075 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hydro-Québec data-center service

    Hydro-Québec · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5316 · Government record · Recorded authority: Official primary

    Source URL

    https://www.hydroquebec.com/data-center/

Counterparties and capital

Hydro-Québec · Utility provider · CMP-1598

Vantage Data Centers · Developer · CMP-0109

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.