Vantage OH1 New Albany Data Center Campus
PRJ-0820 · Site · New Albany, Ohio, United States
Record last updated Oct 28, 2026
Scope and capacity
Vantage OH1 New Albany Data Center Campus, also known as Vantage OH1 New Albany, is a data center project in New Albany, OH, US associated with Vantage Data Centers. 70-acre campus; three 64 MW data centers; 1.5 million square feet; 192 MW critical IT load at full build. AEP Ohio-served campus with diverse utility feeds, closed-loop chilled-water cooling and carrier-neutral fiber access.
Headline: 192 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · Vantage OH1 New Albany | New Albany | OH | US
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 61827 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Lifecycle status · Partially operational
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 61828 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Reported capacity · 192 MW
Design · Vantage OH1 New Albany Data Center Campus (Project)
Claim 61829 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Capacity basis · Vantage Data Centers publishes 192 MW of critical IT capacity for this record boundary.
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 61830 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Location context · Vantage OH1 New Albany | New Albany | OH | US
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97047 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Lifecycle status · Partially operational
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97048 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Reported capacity · 192 MW
Planned / design or future potential · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97049 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Capacity basis · 192 MW facility or campus design capacity.
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97050 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage OH1 New Albany profile
Vantage Data Centers · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3430 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio
Project boundary · Vantage OH1 New Albany
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97052 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage current global data-center portfolio
Vantage Data Centers · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5309 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/
https://vantage-dc.com/data-center-locations/
Location context · New Albany, OH, US
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97053 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage current global data-center portfolio
Vantage Data Centers · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5309 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/
https://vantage-dc.com/data-center-locations/
Lifecycle status · Partially operational
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97054 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage current global data-center portfolio
Vantage Data Centers · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5309 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/
https://vantage-dc.com/data-center-locations/
Development detail · 70-Acre campus; three 64 MW data centers; 1.5 million square feet; 192 MW critical IT load at full build.
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97055 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage current global data-center portfolio
Vantage Data Centers · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5309 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/
https://vantage-dc.com/data-center-locations/
Capacity basis · 192 MW facility or campus design capacity.
Actual · Vantage OH1 New Albany Data Center Campus (Project)
Claim 97056 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage current global data-center portfolio
Vantage Data Centers · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5309 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/
https://vantage-dc.com/data-center-locations/
Counterparties and capital
Vantage Data Centers · Developer · CMP-0109
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.