PRJ-0583 · Site · Sparks / Reno market, Nevada, United States

Captured 2026-09-06T04:12:54.742Z · Record last updated 2026-08-26

SHA-256: 8f383ad3c8223e0d4b128023d63dd34bd2dd830a03ce161b005d9f8686a76a5f

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Vantage announced a four-building, 224 MW AI campus in Storey County, Nevada in July 2025. The operator continues to list the first facility for a second-quarter 2026 opening.

Headline: 224 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Development Status · Construction / delivery unverified

actual · Vantage NV1 Reno Campus (project)

Claim 53245 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Site Area · 137 acres

actual · Vantage NV1 Reno Campus (project)

Claim 53246 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Building Count · 4 facilities

forecast · Vantage NV1 Reno Campus (project)

Claim 53247 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Gross Area · 1,100,000 square feet

forecast · Vantage NV1 Reno Campus (project)

Claim 53248 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Critical It Load · 224 MW

Planned / design or future potential · Vantage NV1 Reno Campus (project)

Claim 53249 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

Headline treatment: Selected headline

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

First Two Buildings Lease Status · Fully leased

actual · Vantage NV1 Reno Campus (project)

Claim 53250 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Primary

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/

First Facility Target Opening · 2026-Q2

Planned / design or future potential · Vantage NV1 Reno Campus (project)

Claim 53251 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

On Site Substation Capacity · 500 MW

forecast · Vantage NV1 Reno Campus (project)

Claim 53252 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Power Provider · NV Energy

forecast · Vantage NV1 Reno Campus (project)

Claim 53253 · Review: Approved · Claim date: Not published

  1. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Project Investment · $nearly 3000000000

transaction scope · Vantage NV1 Reno Campus (project)

Claim 53254 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Primary

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/

Power Density Range · 360 To 720+ W/ft²

reported rounded · Vantage NV1 Reno Campus (project)

Claim 53255 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Cooling Design · Closed loop chilled water with liquid cooling option

design · Vantage NV1 Reno Campus (project)

Claim 53256 · Review: Approved · Claim date: 2025-07-15T00:00:00+00:00

  1. Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Growing Nevada Market

    Vantage Data Centers · Document date: 2025-07-15 · Corroborating

    https://vantage-dc.com/news/vantage-data-centers-invests-3-billion-to-deliver-ai-campus-in-growing-nevada-market/
  2. Reno NV1 Data Center Campus

    Vantage Data Centers · Document date: Not published · Primary

    https://vantage-dc.com/data-center-locations/north-america/reno-nevada/

Counterparties and capital

Economic Development Authority of Western Nevada · Government Authority · CMP-1354

NV Energy · Utility Provider · CMP-0646

Storey County · Government Authority · CMP-0649

Vantage Data Centers · Operator · CMP-0109

Investment Commitment

Amount not disclosed · 2025-07-15

Nearly $3B planned campus investment; no lender, close or spent-to-date allocation disclosed. Source wording: nearly USD 3 billion.

Vantage Data Centers (Sponsor)

Financing record 166; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.