Vantage KUL1 Cyberjaya Data Center Campus

Cyberjaya, Selangor, MalaysiaOperating
Evidence
Planned critical IT
31 MW
Updated
Oct 28, 2026
Utility
Tenaga Nasional Berhad

On December 3, 2025, Vantage announced that the 16 MW KUL14 facility was operational and fully leased to a single customer, completing development of KUL1. KUL14 forms part of the campus total rather than an addition to it. Vantage KUL1 Cyberjaya Data Center Campus, also known as Vantage KUL1 Cyberjaya I, is a data center project in Cyberjaya, Selangor, MY associated with Vantage Data Centers. Six-acre campus; four multi-story data centers; 463,000 square feet at full development; 31 MW critical IT capacity. Carrier-neutral Cyberjaya campus with resilient electrical systems, low-water cooling and extensive connectivity.

Capacity

Reported capacity

Design

31 MW

Source

Reported capacity

Planned / design or future potential

31 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

31 MW is the operator-published facility or campus design boundary.

Participants

Vantage Data Centers

Developer

Sources by role
Developer (1)
Other participants (1)
Tenaga Nasional Berhad

Utility provider

Sources by role
Utility provider (1)

Site & development

Location context

Actual

Vantage KUL1 Cyberjaya I | Cyberjaya | Selangor | MY

Source

Location context

Actual

Vantage KUL1 Cyberjaya I | Cyberjaya | Selangor | MY

Source

Location context

Actual

Cyberjaya, Selangor, MY

Source

Development detail

Actual

Six acre campus; four multi story data centers; 463,000 square feet at full development; 31 MW critical IT capacity.

Source

Additional project facts

Lifecycle status

Actual

Operational

Source

Capacity basis

Actual

Vantage Data Centers publishes 31 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

31 MW facility or campus design capacity.

Source

Project boundary

Actual

Vantage KUL1 Cyberjaya I

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

31 MW facility or campus design capacity.

Source

Infrastructure & permits

Technical details (3)
Electric grid

Energized

Carrier-neutral Cyberjaya campus with resilient electrical systems, low-water cooling and extensive connectivity.

Cooling system

Operational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Electric grid

Energized

31 MW IT design

TNB supplies multiple diverse feeds; adjacent KUL2 capacity is excluded.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Equinix KL2 Cyberjaya

Preconstruction · Cyberjaya, Selangor, Malaysia

Same locality: Cyberjaya

Compare in a collection