Vantage KIX1 Osaka Campus

PRJ-0536 · Site · Ibaraki, Osaka, Japan

Record last updated Oct 28, 2026

Scope and capacity

KIX1 is Vantage's two-building Osaka campus, planned for up to 68 MW of critical IT load.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project identity · Vantage KIX1 Osaka Campus

Source report · Vantage KIX1 Osaka Campus (Project)

Claim 132379 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Osaka (KIX1) data center campus

    Vantage Data Centers · Document date: Not stated · Primary

    Source reference: SRC-7085 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/data-center-locations/apac/osaka-japan/

  2. Vantage Data Centers breaks ground on first campus in Japan

    Vantage Data Centers · Document date: May 22, 2024 · Primary

    Source reference: SRC-7084 · Company announcement · Recorded authority: Party primary

    Source URL

    https://vantage-dc.com/news/vantage-data-centers-breaks-ground-on-first-campus-in-japan/

Counterparties and capital

Vantage Data Centers · Operator · CMP-0109

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.