Skip to content

Vantage KIX1 Osaka Campus

Ibaraki, Osaka, JapanUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

KIX1 is Vantage's two-building Osaka campus, planned for up to 68 MW of critical IT load.

Constituent sites / phases

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Two-facility campus buildUnder construction

2 buildings

68 MW critical IT campus ceiling; facility delivery remains separate.

Milestones (1)
Vantage broke ground on KIX1

May 22, 2024 · Recorded actual event

Completed · Construction started

Source not linked

Participants

Vantage Data Centers

Operator

Sources by role

Additional project facts

Project identity

Source report

Vantage KIX1 Osaka Campus

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

68 MW IT

Campus ceiling across two facilities.

Public-source research. Plans may change. See Evidence for sources and qualifications.