Skip to content
← Return to profile

Cartis diligence evidence schedule

Vantage JNB1 Johannesburg Data Center Campus

PRJ-0844 · Site · Midrand, Johannesburg, Gauteng, South Africa

Captured 2026-09-06T04:13:59.386Z · Record last updated 2026-08-28

SHA-256: 35adec2377e5a63f256ea9d58fce6b666aeb71a2f0a361ac135370ae14389527

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Vantage JNB1 Johannesburg Data Center Campus, also known as Vantage JNB1 Johannesburg I, is a data center project in Midrand, Johannesburg, Gauteng, ZA associated with Vantage Data Centers. 30-acre Waterfall City campus; three data centers at full build; 650,000 square feet; 120 MW critical IT capacity. High-density campus with resilient power, closed-loop cooling and carrier-neutral connectivity near major cloud on-ramps. The current JNB1 project page markets 120 MW at full build, while Vantage’s 2022 opening release and current EMEA rollup imply an 80 MW JNB1 plan alongside 20 MW JNB2. the conflicting operator figures remain unresolved. Current operator evidence conflicts materially and does not establish a single project-scoped capacity figure.

Headline: 120 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 62598 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Lifecycle Status · Partially operational

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 62599 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Reported Capacity · 120 MW

design · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 62600 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Capacity Basis · Vantage Data Centers publishes 120 MW of critical IT capacity for this record boundary.

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 62601 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Location Context · Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 97282 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Lifecycle Status · Partially operational

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 97283 · Review: Approved · Claim date: Not published

  1. Vantage Data Centers Vantage JNB1 Johannesburg I profile

    Vantage Data Centers · Document date: 2026-08-28 · Primary

    https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/

Site Area · 30 acres

actual · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 97289 · Review: Approved · Claim date: Not published

  1. Vantage opens first JNB1 facility

    Vantage Data Centers · Document date: 2022-07-25 · Primary

    https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/

Building Count · 3 data centers

design · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 97290 · Review: Approved · Claim date: Not published

  1. Vantage opens first JNB1 facility

    Vantage Data Centers · Document date: 2022-07-25 · Primary

    https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/

Announced Investment · More than $1 billion

transaction scope · Vantage JNB1 Johannesburg Data Center Campus (project)

Claim 97291 · Review: Approved · Claim date: Not published

  1. Vantage opens first JNB1 facility

    Vantage Data Centers · Document date: 2022-07-25 · Primary

    https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/

Counterparties and capital

Eskom · Utility Provider · CMP-0712

Vantage Data Centers · Developer · CMP-0109

Investment Commitment

$1,000,000,000 · 2022-07-25

Operator described investment as more than $1 billion for the campus; recorded conservatively as the disclosed floor.

Vantage Data Centers (Borrower)

Financing record 192; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.