Cartis diligence evidence schedule
Vantage JNB1 Johannesburg Data Center Campus
PRJ-0844 · Site · Midrand, Johannesburg, Gauteng, South Africa
Record last updated Oct 28, 2026
Scope and capacity
Vantage JNB1 Johannesburg Data Center Campus, also known as Vantage JNB1 Johannesburg I, is a data center project in Midrand, Johannesburg, Gauteng, ZA associated with Vantage Data Centers. 30-acre Waterfall City campus; three data centers at full build; 650,000 square feet; 120 MW critical IT capacity. High-density campus with resilient power, closed-loop cooling and carrier-neutral connectivity near major cloud on-ramps. The current JNB1 project page markets 120 MW at full build, while Vantage’s 2022 opening release and current EMEA rollup imply an 80 MW JNB1 plan alongside 20 MW JNB2. the conflicting operator figures remain unresolved. Current operator evidence conflicts materially and does not establish a single project-scoped capacity figure.
Headline: 120 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (9)
Location context · Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 62598 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Lifecycle status · Partially operational
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 62599 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Reported capacity · 120 MW
Design · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 62600 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Capacity basis · Vantage Data Centers publishes 120 MW of critical IT capacity for this record boundary.
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 62601 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Location context · Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 97282 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Lifecycle status · Partially operational
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 97283 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage Data Centers Vantage JNB1 Johannesburg I profile
Vantage Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3484 · Fact sheet · Recorded authority: Official primary
Source URL
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
https://vantage-dc.com/data-center-locations/emea/johannesburg-i-south-africa/
Site area · 30 acres
Actual · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 97289 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Vantage opens first JNB1 facility
Vantage Data Centers · Document date: Jul 25, 2022 · Primary
Source reference: SRC-5368 · Company announcement · Recorded authority: Official primary
Source URL
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
Building count · 3 data centers
Design · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 97290 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Vantage opens first JNB1 facility
Vantage Data Centers · Document date: Jul 25, 2022 · Primary
Source reference: SRC-5368 · Company announcement · Recorded authority: Official primary
Source URL
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
Announced investment · More than $1 billion
Transaction scope · Vantage JNB1 Johannesburg Data Center Campus (Project)
Claim 97291 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Not stated
- Vantage opens first JNB1 facility
Vantage Data Centers · Document date: Jul 25, 2022 · Primary
Source reference: SRC-5368 · Company announcement · Recorded authority: Official primary
Source URL
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
https://vantage-dc.com/news/vantage-data-centers-opens-johannesburg-data-center-campus-breaks-ground-on-additional-data-center-in-frankfurt/
Counterparties and capital
Eskom · Utility provider · CMP-0712
Vantage Data Centers · Developer · CMP-0109
$1,000,000,000 · Jul 25, 2022
Operator described investment as more than $1 billion for the campus; recorded conservatively as the disclosed floor.
Vantage Data Centers (Borrower)
Sources (1)
- Vantage opens first JNB1 facility · Jul 25, 2022
Financing record 192; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.