Vantage JNB1 Johannesburg Data Center Campus

Midrand, Johannesburg, Gauteng, South AfricaPartially operational
Capacity
120 MW
Planned critical IT
Lead participant
Vantage Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Vantage JNB1 Johannesburg Data Center Campus

Vantage JNB1 Johannesburg Data Center Campus, also known as Vantage JNB1 Johannesburg I, is a data center project in Midrand, Johannesburg, Gauteng, ZA associated with Vantage Data Centers. 30-acre Waterfall City campus; three data centers at full build; 650,000 square feet; 120 MW critical IT capacity. High-density campus with resilient power, closed-loop cooling and carrier-neutral connectivity near major cloud on-ramps. The current JNB1 project page markets 120 MW at full build, while Vantage’s 2022 opening release and current EMEA rollup imply an 80 MW JNB1 plan alongside 20 MW JNB2. the conflicting operator figures remain unresolved. Current operator evidence conflicts materially and does not establish a single project-scoped capacity figure.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load120 MWDesign · Vantage JNB1 Johannesburg Data Center Campus

Development

1 phases · 1 milestones
JNB1 phased campusPartially Operational

16 MW operating first building; 80 MW earlier full-build plan; 120 MW current project-page plan. Headline withheld.

3 buildings

Jul 25, 2022
First 16 MW JNB1 facility opened
Completed

Infrastructure

Electric GridEnergized

High-density campus with resilient power, closed-loop cooling and carrier-neutral connectivity near major cloud on-ramps.

Cooling SystemOperational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

9 facts
Location Context
Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
120 MW
Design
Capacity Basis
Vantage Data Centers publishes 120 MW of critical IT capacity for this record boundary.
Actual
Location Context
Vantage JNB1 Johannesburg I | Midrand, Johannesburg | Gauteng | ZA
Actual
Lifecycle Status
Partially operational
Actual
Site Area
30 acres
Actual
Building Count
3 data centers
Design
Announced Investment
More than $1 billion
Transaction Scope