Vantage Frontier / Stargate Shackelford
- Planned critical IT
- 1,400 MW
- Updated
- Oct 28, 2026
Vantage's Frontier campus in Shackelford County is under construction for Oracle/OpenAI Stargate. Vantage plans 1.4 GW of critical IT capacity and ten buildings, not a verified operating load. Its first-building forecast remains H2 2026, while Oracle says customer delivery begins in H1 2027; these milestones are not interchangeable. Official building records extend into 2027. The design combines onsite gas generation with closed-loop cooling and planned diverse fiber paths. Public records identify building-level Vantage owners and Oracle occupants/operators. Site-specific financing closure and current metered IT load remain unverified.
This record and Frontier Texas describe overlapping Frontier campus scope. Do not add their 1,400 MW figures together. Related record
Capacity
Rack density
Planned / design or future potential250+ kW
Power density; not a whole-site capacity
SourceABI-1 proposed installed generation — July 2025 review 180842, not later application 182467
Proposed generation, not operating IT load709 MW
Generation capacity; not IT capacity
SourceOnsite generation infrastructure
DesignOracle describes onsite gas reciprocating engines; ABI-1 is connected generation, not IT capacity. system
Generation capacity; not IT capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Participants
Developer
Cloud operator
Customer
Generation developer
Registered owner — TX301 building only, not whole campus fee title
Registered operator
Other participants (1)
Registered occupant
Capital & incentives
Capital claims
Site & development
Technical specifications
Cooling infrastructure
PlannedClosed loop chiller with air/liquid to liquid systems, N+1 mechanical. Design, not measured cooling efficiency. system
SourceFiber infrastructure
PlannedDiverse dark/lit paths, three MMRs per building. AT&T, Fiberlight, Windstream and Zayo nearby does not mean contracted/on net. system
SourceWater infrastructure
DesignOracle describes one time fill and non evaporative loop; named source supplier and measured total consumption not established. system
SourceAdditional project facts
Oracle customer delivery begins H1 2027
Forecast; half year precisionH1 2027 — forecast milestone
SourceABI-1 180842 permit or registration record
Air standard permit technical reviewTechnical review signed; review/notice/registration date 2025-07-17. Technical review signed; standalone authorization, full amendment history and actual generation not established. regulatory record
SourceABI-1 182467 / PSDTX1692 / GHGPSDTX266 permit or registration record
Air permit applicationPending; review/notice/registration date 2025-12-17. Notice date is not issuance. Application remains on pending list inspected October 27, 2026; final action and actual operation not established. regulatory record
SourceTX301 TABS2026024068 permit or registration record
Building accessibility registrationReview complete; review/notice/registration date 2026-06-29. Accessibility review complete is not construction complete. Registered completion estimate August 11, 2027. regulatory record
SourceQualifying large data center certification
CertifiedTX301–TX310 certification effective October 8, 2025. No exemption savings quantified. Certification is not commissioning, utilization or proof of realized tax benefits. incentive scope
SourceInfrastructure & permits
Technical details (7)
Design
closed-loop liquid chiller
Reported plan
behind-the-meter natural-gas microgrid
Proposed generation, not operating IT load
709 MW
Design
Oracle describes onsite gas reciprocating engines; ABI-1 is connected generation, not IT capacity.
Planned
Closed-loop chiller with air/liquid-to-liquid systems, N+1 mechanical. Design, not measured cooling efficiency.
Planned
Diverse dark/lit paths, three MMRs per building. AT&T, Fiberlight, Windstream and Zayo nearby does not mean contracted/on-net.
Design
Oracle describes one-time fill and non-evaporative loop; named source supplier and measured total consumption not established.
Project map
ABI-1 180842 permit or registration record · Technical review signed; review/notice/registration date 2025-07-17. Technical review signed; standalone authorization, full amendment history and actual generation not established.
Vantage Frontier / Stargate Shackelford
ABI-1 182467 / PSDTX1692 / GHGPSDTX266 permit or registration record · Pending; review/notice/registration date 2025-12-17. Notice date is not issuance. Application remains on pending list inspected October 27, 2026; final action and actual operation not established.
Vantage Frontier / Stargate Shackelford
TX301 TABS2026024068 permit or registration record · Review complete; review/notice/registration date 2026-06-29. Accessibility review complete is not construction complete. Registered completion estimate August 11, 2027.
Vantage Frontier / Stargate Shackelford
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (2)
Operating · Abilene, Texas, United States
Shared participant: Oracle · Shared participant: OpenAI · Same market: Texas, United States
Compare in a collectionUnder construction · Texas, United States
Shared developer: Vantage Data Centers · Same market: Texas, United States
Compare in a collection