Cartis diligence evidence schedule

True IDC Eastern Economic Corridor AI Data Center

PRJ-0649 · Site · Chonburi, Thailand

Record last updated Oct 28, 2026

Scope and capacity

True IDC has broken ground on an AI-ready mega data center in Thailand’s Eastern Economic Corridor. The company states total power of up to 250 MW, with the first phase planned to enter operation in 2027. AI-ready hyperscale design in the Eastern Economic Corridor.

Headline: 250 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · True IDC EEC campus | Chonburi | Thailand

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 56295 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

Lifecycle status · Construction

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 56296 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

Reported capacity · 250 MW

Planned / design or future potential · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 56297 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

Capacity basis · True IDC announcement states total power of up to 250 MW.

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 56298 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

Project identity · True IDC Eastern Economic Corridor AI Data Center

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114735 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Lifecycle status · Under construction

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114736 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Location · Chonburi, Chonburi, TH

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114737 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Participant roles · True IDC

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114738 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Capacity · 250 MW

Planned / design or future potential · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114739 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Capacity basis · 250 MW planned or design IT capacity

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114740 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Development scale · Up to 250 MW total power; first phase planned for 2027.

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114741 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Infrastructure · AI-ready hyperscale design in the Eastern Economic Corridor.

Actual · True IDC Eastern Economic Corridor AI Data Center (Project)

Claim 114742 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. True IDC breaks ground on new EEC data center

    True IDC · Document date: Mar 31, 2026 · Primary

    Source reference: SRC-3048 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.trueidc.com/en/news-detail/232/new-data-center-groundbreaking-EEC

  2. Thailand investment framework for data centers

    Thailand Board of Investment · Document date: Jan 1, 2026 · Corroborating

    Source reference: SRC-6402 · Government record · Recorded authority: Official primary

    Source URL

    https://www.boi.go.th/upload/content/BOI%20-%20Navigating%20Investment%20for%20New%20Industries_EN.pdf

Counterparties and capital

True IDC · Developer · CMP-1399

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.