Skip to content
All records
Data center siteSite record

True IDC Eastern Economic Corridor AI Data Center

Chonburi, ThailandUnder construction
Capacity
250 MW
Planned / design
Lead participant
True IDC
Developer
Last updated
Aug 27, 2026
Most recent public record update

About True IDC Eastern Economic Corridor AI Data Center

True IDC has broken ground on an AI-ready mega data center in Thailand’s Eastern Economic Corridor. The company states total power of up to 250 MW, with the first phase planned to enter operation in 2027. AI-ready hyperscale design in the Eastern Economic Corridor.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design250 MWDesign · True IDC Eastern Economic Corridor AI Data Center
Design250 MWDesign · True IDC Eastern Economic Corridor AI Data Center

Development

1 phases · 2 milestones
Construction programUnder Construction

True IDC Eastern Economic Corridor AI Data Center: Under construction.

Mar 31, 2026
True IDC Eastern Economic Corridor AI Data Center: Groundbreaking completed; first phase planned for 2027.
In Progress
True IDC Eastern Economic Corridor AI Data Center — Under construction
In Progress

Infrastructure

Electric GridPlanned Or Represented

250 MW

250 MW planned or design IT capacity

Site FacilityPlanned Or Represented

AI-ready hyperscale design in the Eastern Economic Corridor.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
True IDC EEC campus | Chonburi | Thailand
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
250 MW
Design
Capacity Basis
True IDC announcement states total power of up to 250 MW.
Actual
Project Identity
True IDC Eastern Economic Corridor AI Data Center
Actual
Lifecycle Status
Under construction
Actual
Location
Chonburi, Chonburi, TH
Actual
Participant Roles
True IDC
Actual
Capacity
250 MW
Design
Capacity Basis
250 MW planned or design IT capacity
Actual
Development Scale
Up to 250 MW total power; first phase planned for 2027.
Actual
Infrastructure
AI-ready hyperscale design in the Eastern Economic Corridor.
Actual