Cartis diligence evidence schedule

Trammell Crow Georgia Campus

PRJ-1089 · Site · Social Circle, Georgia, United States

Record last updated Aug 28, 2026

Scope and capacity

The Trammell Crow Georgia Campus record tracks a proposed large data-center development near Social Circle, Georgia. Public planning coverage supports the existence of a major phased campus, but the tracked 2.4 GW value has not been verified in a project-specific developer release, utility filing or final permit as operating or committed capacity. Exact legal applicant, building program, power-delivery agreement, water plan, incentives, permits and construction timing require follow-up.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Trammell Crow Georgia Campus | Social Circle | Georgia | US

Actual · Trammell Crow Georgia Campus (Project)

Claim 70328 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Trammell Crow Georgia Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4013 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-proposed-data-centers

Lifecycle status · Proposed

Actual · Trammell Crow Georgia Campus (Project)

Claim 70329 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Trammell Crow Georgia Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4013 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-proposed-data-centers

Capacity basis · 2,400 MW future full build site capacity; not measured operating IT load.

Actual · Trammell Crow Georgia Campus (Project)

Claim 70331 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Trammell Crow Georgia Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4013 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-proposed-data-centers

Location context · Trammell Crow Georgia Campus | Social Circle | Georgia | US

Actual · Trammell Crow Georgia Campus (Project)

Claim 74522 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Trammell Crow Georgia Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4013 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-proposed-data-centers

Lifecycle status · Proposed

Actual · Trammell Crow Georgia Campus (Project)

Claim 74523 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Trammell Crow Georgia Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4013 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-proposed-data-centers

Developer association · Trammell Crow Company

Actual · Trammell Crow Georgia Campus (Project)

Claim 74526 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Georgia data-center industry resources

    Georgia Department of Economic Development · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4242 · Government record · Recorded authority: Official primary

    Source URL

    https://georgia.org/industries/technology/data-centers

Location context · Social Circle, Georgia

Actual · Trammell Crow Georgia Campus (Project)

Claim 74527 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Georgia data-center industry resources

    Georgia Department of Economic Development · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4242 · Government record · Recorded authority: Official primary

    Source URL

    https://georgia.org/industries/technology/data-centers

Capacity status · 2.4 GW remains unverified project specifically

Actual · Trammell Crow Georgia Campus (Project)

Claim 74528 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Georgia data-center industry resources

    Georgia Department of Economic Development · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4242 · Government record · Recorded authority: Official primary

    Source URL

    https://georgia.org/industries/technology/data-centers

Counterparties and capital

Trammell Crow Company · Developer · CMP-1501

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.