Tract Illinois (Morris)

PRJ-1139 · Site · Morris, Illinois, United States

Record last updated Oct 28, 2026

Scope and capacity

Tract’s Morris Technology Park is a 343-acre, fully annexed and zoned data-center development outside Chicago. Public reporting describes roughly 2.9 million square feet, up to 1 GW at full buildout, initial energization targeted for June 2028 and a ramp to full load by 2032.

Headline: 1,000 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Tract Illinois (Morris) | Morris | Illinois | US

Actual · Tract Illinois (Morris) (Project)

Claim 71878 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Tract Illinois (Morris) public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4123 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/illinois/

Lifecycle status · Proposed

Actual · Tract Illinois (Morris) (Project)

Claim 71879 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Tract Illinois (Morris) public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4123 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/illinois/

Reported capacity · 1,000 MW

Planned / design or future potential · Tract Illinois (Morris) (Project)

Claim 71880 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Tract Illinois (Morris) public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4123 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/illinois/

Capacity basis · 1,000 MW future full build site capacity; not measured operating IT load.

Actual · Tract Illinois (Morris) (Project)

Claim 71881 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Tract Illinois (Morris) public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4123 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/illinois/

Site area · 343 acres

Reported rounded · Tract Illinois (Morris) (Project)

Claim 77766 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Tract expands into Illinois

    Data Center Dynamics · Document date: Jan 16, 2026 · Primary

    Source reference: SRC-4424 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/tract-expands-into-illinois-with-plans-for-1gw-data-center-park-outside-chicago/

Gross floor area · 2,900,000 square feet

Reported rounded · Tract Illinois (Morris) (Project)

Claim 77767 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Tract expands into Illinois

    Data Center Dynamics · Document date: Jan 16, 2026 · Primary

    Source reference: SRC-4424 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/tract-expands-into-illinois-with-plans-for-1gw-data-center-park-outside-chicago/

Target initial energization · June 2028

Reported rounded · Tract Illinois (Morris) (Project)

Claim 77768 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Tract expands into Illinois

    Data Center Dynamics · Document date: Jan 16, 2026 · Primary

    Source reference: SRC-4424 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/tract-expands-into-illinois-with-plans-for-1gw-data-center-park-outside-chicago/

Target full load · 2032

Reported rounded · Tract Illinois (Morris) (Project)

Claim 77769 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Tract expands into Illinois

    Data Center Dynamics · Document date: Jan 16, 2026 · Primary

    Source reference: SRC-4424 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/tract-expands-into-illinois-with-plans-for-1gw-data-center-park-outside-chicago/

Counterparties and capital

Tract · Developer · CMP-1271

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.