Data center siteSite record
Tract Illinois (Morris)
Morris, Illinois, United StatesProposed
Capacity
1,000 MW
Planned / design
Lead participant
Tract
Developer
Last updated
Aug 28, 2026
Most recent public record update
About Tract Illinois (Morris)
Tract’s Morris Technology Park is a 343-acre, fully annexed and zoned data center development outside Chicago. Public reporting describes roughly 2.9 million square feet, up to 1 GW at full buildout, initial energization targeted for June 2028 and a ramp to full load by 2032.
Capacity
Planned / designOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
Future Potential1,000 MWDesign · Tract Illinois (Morris)
Development
1 phases · 2 milestonesEntitled development and utility deliveryAnnounced Or Preconstruction
Tract’s Morris Technology Park is a 343-acre, fully annexed and zoned data center development outside Chicago. Public reporting describes roughly 2.9 million square feet, up to 1 GW at full buildout, initial energization targeted for June 2028 and a ramp to full load by 2032.
Jan 16, 2026
Morris Technology Park publicly announced
CompletedJun 1, 2028
Target initial energization
ForecastInfrastructure
Electric GridPlanned Or Represented
1,000 MW
ComEd capacity reported as secured; full ramp targeted by 2032.
Project map
0 of 1 project point mappedInfrastructure facts
1
Mapped records
1
Capacity figures
1
No map point available
Power & interconnection: 1
Facts & sources
Published claims and their source links.
Location ContextTract Illinois (Morris) | Morris | Illinois | USActual
Tract Illinois (Morris) | Morris | Illinois | US
Lifecycle StatusProposedActual
Proposed
Reported Capacity1,000 MWDesign
1,000 MW
Capacity Basis1,000 MW future full build site capacity; not measured operating IT load.Actual
1,000 MW future full build site capacity; not measured operating IT load.
Site Area343 acresReported Rounded
343 acres
Gross Floor Area2,900,000 square feetReported Rounded
2,900,000 square feet
Target Initial EnergizationJune 2028Reported Rounded
June 2028
Target Full Load2032Reported Rounded
2032