1,000 MW
Updated
Oct 28, 2026

Tract’s Morris Technology Park is a 343-acre, fully annexed and zoned data center development outside Chicago. Public reporting describes roughly 2.9 million square feet, up to 1 GW at full buildout, initial energization targeted for June 2028 and a ramp to full load by 2032.

Capacity

Reported capacity

Planned / design or future potential

1,000 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Entitled development and utility deliveryAnnounced or preconstruction

Tract’s Morris Technology Park is a 343-acre, fully annexed and zoned data center development outside Chicago. Public reporting describes roughly 2.9 million square feet, up to 1 GW at full buildout, initial energization targeted for June 2028 and a ramp to full load by 2032.

Milestones (2)
Morris Technology Park publicly announced

Jan 16, 2026 · Recorded actual event

Completed · Announced

Source not linked
Target initial energization

Jun 2028 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Tract

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Tract Illinois (Morris) | Morris | Illinois | US

Source

Site area

Reported rounded

343 acres

Source

Gross floor area

Reported rounded

2,900,000 square feet

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

1,000 MW future full build site capacity; not measured operating IT load.

Source

Target initial energization

Reported rounded

June 2028

Source

Target full load

Reported rounded

2032

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

1,000 MW

ComEd capacity reported as secured; full ramp targeted by 2032.