TeraWulf Chesapeake Data & Energy Campus

PRJ-0696 · Site · Morgantown, Maryland, United States

Record last updated Oct 28, 2026

Scope and capacity

TeraWulf is advancing Chesapeake Data & Energy at the Morgantown generation site in Charles County. The company identifies approximately 800 MW of planned critical IT capacity within a larger integrated generation, storage and load design. TeraWulf is associated with the development in Morgantown, Charles County, MD, US. The disclosed development scope includes approximately 800 MW planned critical IT; existing 210 MW generation; initial data-center operations contemplated for 2030. Power and physical infrastructure include legacy generation and transmission site with planned on-site generation and battery storage. TeraWulf identifies about 800 MW of planned critical IT capacity.

Headline: 800 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Chesapeake Data & Energy | Morgantown | Charles County | Maryland

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 57924 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Lifecycle status · Permitted

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 57925 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Reported capacity · 800 MW

Design · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 57926 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Capacity basis · TeraWulf identifies about 800 MW of planned critical IT capacity.

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 57927 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Location context · Chesapeake Data & Energy | Morgantown | Charles County | Maryland

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111331 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Lifecycle status · Permitted

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111332 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Reported capacity · 800 MW

Design · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111333 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Capacity basis · TeraWulf identifies about 800 MW of planned critical IT capacity.

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111334 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

Development scale · Approximately 800 MW planned critical IT

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111351 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

  2. TeraWulf Q2 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Corroborating

    Source reference: SRC-6233 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm

Development milestone · Existing 210 MW generation

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111352 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

  2. TeraWulf Q2 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Corroborating

    Source reference: SRC-6233 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm

Power arrangement · Initial data center operations contemplated for 2030.

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111353 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

  2. TeraWulf Q2 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Corroborating

    Source reference: SRC-6233 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm

Site configuration · Chesapeake Data & Energy | Morgantown | Charles County | Maryland

Actual · TeraWulf Chesapeake Data & Energy Campus (Project)

Claim 111354 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TeraWulf reports second-quarter 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Primary

    Source reference: SRC-3157 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results

  2. TeraWulf Q2 2026 results

    TeraWulf · Document date: Aug 5, 2026 · Corroborating

    Source reference: SRC-6233 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm

Counterparties and capital

TeraWulf · Developer · CMP-1389