TeraWulf Chesapeake Data & Energy Campus

Morgantown, Maryland, United StatesEntitled / Permitted
Capacity
800 MW
Planned critical IT
Lead participant
TeraWulf
Developer
Last updated
Aug 27, 2026
Most recent public record update

About TeraWulf Chesapeake Data & Energy Campus

TeraWulf is advancing Chesapeake Data & Energy at the Morgantown generation site in Charles County. The company identifies approximately 800 MW of planned critical IT capacity within a larger integrated generation, storage and load design. TeraWulf is associated with the development in Morgantown, Charles County, MD, US. The disclosed development scope includes approximately 800 MW planned critical IT; existing 210 MW generation; initial data center operations contemplated for 2030. Power and physical infrastructure include legacy generation and transmission site with planned on-site generation and battery storage. TeraWulf identifies about 800 MW of planned critical IT capacity.

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load800 MWDesign · TeraWulf Chesapeake Data & Energy Campus
It Load800 MWDesign · TeraWulf Chesapeake Data & Energy Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Project-wide phase for TeraWulf Chesapeake Data & Energy Campus; capacity class is it load.

Aug 5, 2026
Chesapeake Data Morgantown development disclosed
Completed
Permitting; acquisition and development approvals remain conditions
Forecast

Infrastructure

Electric GridPlanned Or Represented

800 MW

TeraWulf identifies about 800 MW of planned critical IT capacity.

Site FacilityPlanned Or Represented

Legacy generation and transmission site with planned on-site generation and battery storage.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Chesapeake Data & Energy | Morgantown | Charles County | Maryland
Actual
Lifecycle Status
Permitted
Actual
Reported Capacity
800 MW
Design
Capacity Basis
TeraWulf identifies about 800 MW of planned critical IT capacity.
Actual
Location Context
Chesapeake Data & Energy | Morgantown | Charles County | Maryland
Actual
Lifecycle Status
Permitted
Actual
Reported Capacity
800 MW
Design
Capacity Basis
TeraWulf identifies about 800 MW of planned critical IT capacity.
Actual
Development Scale
Approximately 800 MW planned critical IT
Actual
Development Milestone
Existing 210 MW generation
Actual
Power Arrangement
Initial data center operations contemplated for 2030.
Actual
Site Configuration
Chesapeake Data & Energy | Morgantown | Charles County | Maryland
Actual