T1 Giga Arctic Data Center Conversion

PRJ-0706 · Site · Mo i Rana, Nordland, Norway

Record last updated Oct 28, 2026

Scope and capacity

T1 Energy received local approval to convert part of its Giga Arctic industrial campus in Mo i Rana into a data center. The company expects a 50 MW facility could operate in 2027 and holds a longer-term position for 396 MW in the grid queue. T1 Energy is associated with the development in Mo i Rana, Rana Municipality, Nordland, NO. The disclosed development scope includes 50 MW initial planned data center; rezoning approved; 396 MW grid-queue position. Power and physical infrastructure include brownfield industrial building with hydropower access and a grid-queue position. T1 expects that a 50 MW data center could be operational in 2027.

Headline: 50 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Giga Arctic campus | Mo i Rana | Nordland | Norway

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 57964 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Lifecycle status · Permitted

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 57965 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Reported capacity · 50 MW

Planned / design or future potential · T1 Giga Arctic Data Center Conversion (Project)

Claim 57966 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Capacity basis · T1 expects that a 50 MW data center could be operational in 2027.

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 57967 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Location context · Giga Arctic campus | Mo i Rana | Nordland | Norway

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111411 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Lifecycle status · Permitted

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111412 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Reported capacity · 50 MW

Planned / design or future potential · T1 Giga Arctic Data Center Conversion (Project)

Claim 111413 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Capacity basis · T1 expects that a 50 MW data center could be operational in 2027.

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111414 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

Development scale · 50 MW initial planned data center

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111431 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

  2. T1 Giga Arctic Form 8-K index

    T1 Energy · Document date: Jul 28, 2026 · Corroborating

    Source reference: SRC-6249 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1992243/000121390026081970/0001213900-26-081970-index.htm

Development milestone · Rezoning approved

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111432 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

  2. T1 Giga Arctic Form 8-K index

    T1 Energy · Document date: Jul 28, 2026 · Corroborating

    Source reference: SRC-6249 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1992243/000121390026081970/0001213900-26-081970-index.htm

Power arrangement · 396 MW grid queue position.

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111433 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

  2. T1 Giga Arctic Form 8-K index

    T1 Energy · Document date: Jul 28, 2026 · Corroborating

    Source reference: SRC-6249 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1992243/000121390026081970/0001213900-26-081970-index.htm

Site configuration · Giga Arctic campus | Mo i Rana | Nordland | Norway

Actual · T1 Giga Arctic Data Center Conversion (Project)

Claim 111434 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. T1 Giga Arctic approved for data center development

    T1 Energy · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3169 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ir.t1energy.com/news-releases/news-release-details/t1-giga-arctic-approved-data-center-development

  2. T1 Giga Arctic Form 8-K index

    T1 Energy · Document date: Jul 28, 2026 · Corroborating

    Source reference: SRC-6249 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1992243/000121390026081970/0001213900-26-081970-index.htm

Counterparties and capital

T1 Energy · Developer · CMP-1446

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.