Cartis diligence evidence schedule

Switch Las Vegas Core Campus

PRJ-0968 · Site · Las Vegas, Nevada, United States

Record last updated Oct 28, 2026

Scope and capacity

Switch’s Core Campus is an operating, multi-building Las Vegas ecosystem that can reach 495 MW only upon full completion. The profile keeps active air-permit context, renewable-energy claims and the LAS VEGAS 10 milestone separate from measured tenant utilization. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Headline: 495 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (17)

Location context · Switch The Core | Las Vegas | NV | US

Actual · Switch Las Vegas Core Campus (Project)

Claim 66469 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Lifecycle status · Partially operational

Actual · Switch Las Vegas Core Campus (Project)

Claim 66470 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Reported capacity · 495 MW

Design · Switch Las Vegas Core Campus (Project)

Claim 66471 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Capacity basis · Switch publishes 495 MW of IT power for this project boundary.

Actual · Switch Las Vegas Core Campus (Project)

Claim 66472 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Location context · Switch The Core | Las Vegas | NV | US

Actual · Switch Las Vegas Core Campus (Project)

Claim 84384 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Lifecycle status · Partially operational

Actual · Switch Las Vegas Core Campus (Project)

Claim 84385 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Reported capacity · 495 MW

Design · Switch Las Vegas Core Campus (Project)

Claim 84386 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Capacity basis · 495 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Switch Las Vegas Core Campus (Project)

Claim 84387 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Operator confirmed · Switch

Actual · Switch Las Vegas Core Campus (Project)

Claim 84388 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Project location · Las Vegas, NV, US

Actual · Switch Las Vegas Core Campus (Project)

Claim 84389 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Current lifecycle · Partly operating with phased delivery or expansion underway

Actual · Switch Las Vegas Core Campus (Project)

Claim 84390 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Capacity classification · It load

Actual · Switch Las Vegas Core Campus (Project)

Claim 84391 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Capacity basis · 495 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Switch Las Vegas Core Campus (Project)

Claim 84392 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Customer utilization · Not publicly disclosed

Actual · Switch Las Vegas Core Campus (Project)

Claim 84393 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Actual · Switch Las Vegas Core Campus (Project)

Claim 84394 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Active Title V permits

    Clark County Division of Air Quality · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-4733 · Government record · Recorded authority: Official primary

    Source URL

    https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/title-v-permits

Source refresh date · 2026-08-29

Actual · Switch Las Vegas Core Campus (Project)

Claim 84395 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Renewable energy claim · 100 percent

Actual · Switch Las Vegas Core Campus (Project)

Claim 84397 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Las Vegas Core Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3758 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/las-vegas/

Counterparties and capital

Switch · Developer · CMP-0645

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.