Cartis diligence evidence schedule

STT Fairview Campus

PRJ-0439 · Site · Fairview, Quezon City, NCR, Philippines

Record last updated Oct 28, 2026

Scope and capacity

STT Fairview is a 124 MW full-design campus in Quezon City whose first building has begun serving customers while the rest of the campus remains in development.

Headline: 124 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (21)

Physical campus count · 1 campus

Source report · STT Fairview Campus (Project)

Claim 41908 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

  2. STT Fairview factsheet

    ST Telemedia Global Data Centres · Document date: Not stated · Primary

    Source reference: SRC-2353 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/resources/stt-fairview-factsheet

Planned building count · 4 buildings

Source report · STT Fairview Campus (Project)

Claim 41909 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

  2. STT Fairview factsheet

    ST Telemedia Global Data Centres · Document date: Not stated · Primary

    Source reference: SRC-2353 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/resources/stt-fairview-factsheet

Full build floor area · 83,000 square meters

Source report · STT Fairview Campus (Project)

Claim 41910 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

Full campus design capacity · 124 MW IT

Planned / design or future potential · STT Fairview Campus (Project)

Claim 41911 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. STT Fairview campus achieves IDCA G2 design certification

    ST Telemedia Global Data Centres · Document date: Sep 17, 2025 · Primary

    Source reference: SRC-2351 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-ph-flagship-124mw-stt-fairview-campus-achieves-idca-g2-design-certification

  2. STT GDC Philippines tops off STT Fairview 1

    ST Telemedia Global Data Centres · Document date: Dec 18, 2024 · Primary

    Source reference: SRC-2350 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-ph-tops-off-stt-fairview-1

  3. STT Fairview 1 opening Q2 2025

    ST Telemedia Global Data Centres · Document date: Oct 31, 2024 · Primary

    Source reference: SRC-2349 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-fairview-1-opening-q2-2025-positioned-to-support-growing-ai-demand

Full campus capacity is operating load · False

Source report · STT Fairview Campus (Project)

Claim 41912 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines strengthens AI infrastructure

    Globe Telecom · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-2355 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-philippines-ai-digital-infrastructure

  2. STT Fairview 1 opening Q2 2025

    ST Telemedia Global Data Centres · Document date: Oct 31, 2024 · Primary

    Source reference: SRC-2349 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-fairview-1-opening-q2-2025-positioned-to-support-growing-ai-demand

Operating building count minimum · 1 building

Source report · STT Fairview Campus (Project)

Claim 41913 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines strengthens AI infrastructure

    Globe Telecom · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-2355 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-philippines-ai-digital-infrastructure

  2. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

Campus status · Partially operational

Source report · STT Fairview Campus (Project)

Claim 41914 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines strengthens AI infrastructure

    Globe Telecom · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-2355 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-philippines-ai-digital-infrastructure

  2. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

Fairview 1 is first of four buildings · True

Source report · STT Fairview Campus (Project)

Claim 41915 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT Fairview factsheet

    ST Telemedia Global Data Centres · Document date: Not stated · Primary

    Source reference: SRC-2353 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/resources/stt-fairview-factsheet

Liquid cooling ready design · True

Source report · STT Fairview Campus (Project)

Claim 41916 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT Fairview 1 opening Q2 2025

    ST Telemedia Global Data Centres · Document date: Oct 31, 2024 · Primary

    Source reference: SRC-2349 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-fairview-1-opening-q2-2025-positioned-to-support-growing-ai-demand

  2. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

Target leed level · Gold

Source report · STT Fairview Campus (Project)

Claim 41917 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

Target uptime tier · Tier III

Source report · STT Fairview Campus (Project)

Claim 41918 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

Idca g2 design certified · True

Source report · STT Fairview Campus (Project)

Claim 41919 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT Fairview campus achieves IDCA G2 design certification

    ST Telemedia Global Data Centres · Document date: Sep 17, 2025 · Primary

    Source reference: SRC-2351 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-ph-flagship-124mw-stt-fairview-campus-achieves-idca-g2-design-certification

Idca design certification proves operation · False

Source report · STT Fairview Campus (Project)

Claim 41920 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

  2. STT Fairview campus achieves IDCA G2 design certification

    ST Telemedia Global Data Centres · Document date: Sep 17, 2025 · Primary

    Source reference: SRC-2351 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-ph-flagship-124mw-stt-fairview-campus-achieves-idca-g2-design-certification

Virtual metro campus link to makati · True

Source report · STT Fairview Campus (Project)

Claim 41921 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines welcomes connectivity partners

    ST Telemedia Global Data Centres · Document date: Oct 23, 2025 · Primary

    Source reference: SRC-2352 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-philippines-advances-country-digital-readiness-welcomes-globe-radius-source-telecoms-connectivity-partners

Announced connectivity partner count · 3 providers

Source report · STT Fairview Campus (Project)

Claim 41922 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines welcomes connectivity partners

    ST Telemedia Global Data Centres · Document date: Oct 23, 2025 · Primary

    Source reference: SRC-2352 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/stt-gdc-philippines-advances-country-digital-readiness-welcomes-globe-radius-source-telecoms-connectivity-partners

Renewable supply contract total · 40.5 MW

Transaction scope · STT Fairview Campus (Project)

Claim 41923 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Not stated

Headline treatment: Commercial transaction scope; not operating IT load

  1. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

Renewable supply contract allocable to fairview · False

Source report · STT Fairview Campus (Project)

Claim 41924 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

Fairview share of renewable contract disclosed · False

Source report · STT Fairview Campus (Project)

Claim 41925 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

Campus operating IT load disclosed · False

Source report · STT Fairview Campus (Project)

Claim 41926 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines strengthens AI infrastructure

    Globe Telecom · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-2355 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-philippines-ai-digital-infrastructure

Future buildings separately named · False

Source report · STT Fairview Campus (Project)

Claim 41927 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT Fairview factsheet

    ST Telemedia Global Data Centres · Document date: Not stated · Primary

    Source reference: SRC-2353 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/resources/stt-fairview-factsheet

Project financing amount disclosed · False

Source report · STT Fairview Campus (Project)

Claim 41928 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. STT GDC Philippines and MPower sign renewable energy deal

    Globe Telecom · Document date: Apr 23, 2026 · Primary

    Source reference: SRC-2354 · Recorded authority: Party primary

    Source URL

    https://www.globe.com.ph/about-us/newsroom/corporate/stt-gdc-ph-mpower-renewable-energy-deal

  2. STT GDC to build Philippines' largest carrier-neutral data center

    ST Telemedia Global Data Centres · Document date: May 5, 2023 · Primary

    Source reference: SRC-2348 · Recorded authority: Party primary

    Source URL

    https://www.sttelemediagdc.com/newsroom/st-telemedia-global-data-centres-to-build-philippines-largest-and-most-interconnected-carrier-neutral-data-centre

Counterparties and capital

International Data Center Authority · Contractor · CMP-1091

MPower · Supplier · CMP-1088

STT GDC Philippines · Operator · CMP-1085

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.