Scope and capacity

On September 21, 2026, Lovejoy adopted an immediately effective citywide prohibition on data centers. This is subsequent regulatory context for the already withdrawn Stillwater proposal, not a second cancellation event or a revival of its historical capacity plans. A withdrawn proposal at Panhandle Road. Historical service and development envelopes. Stillwater Technology Park — Lovejoy is located in Lovejoy, GA, US and is a data center campus in cancelled status.

Headline: 1,250 MW Utility capacity

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Proposal site address · 11760 Panhandle Road

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32181 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. DRI Initial Information Form #4794 — Stillwater Technology Park

    Georgia Department of Community Affairs · Document date: Not stated · Primary

    Source reference: SRC-1819 · Recorded authority: Official primary

    Source URL

    https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4794

Historical proposed floor area · 3,465,000 square feet

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32182 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. DRI Initial Information Form #4794 — Stillwater Technology Park

    Georgia Department of Community Affairs · Document date: Not stated · Primary

    Source reference: SRC-1819 · Recorded authority: Official primary

    Source URL

    https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4794

Historical rezoning area · 363.71 acres

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32183 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City Council Agenda — December 15, 2025

    City of Lovejoy · Document date: Dec 15, 2025 · Primary

    Source reference: SRC-1820 · Recorded authority: Official primary

    Source URL

    https://www.cityoflovejoy.com/DocumentCenter/View/2799/Agenda---DEC-15

Historical reported building count · 15 buildings

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32184 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Proposal for Clayton County data center withdrawn

    Atlanta News First · Document date: Aug 7, 2026 · Corroborating

    Source reference: SRC-1822 · News report · Recorded authority: Secondary

    Source URL

    https://www.cbs46.com/2026/08/07/proposal-clayton-county-data-center-withdrawn/

  2. Gigawatt-scale data center campus planned outside Atlanta, Georgia

    Data Center Dynamics · Document date: Jul 27, 2026 · Primary

    Source reference: SRC-1821 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/gigawatt-scale-data-center-campus-planned-outside-atlanta-georgia/

Historical proposed grid connection · 1.25 GW

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32186 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Gigawatt-scale data center campus planned outside Atlanta, Georgia

    Data Center Dynamics · Document date: Jul 27, 2026 · Primary

    Source reference: SRC-1821 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/gigawatt-scale-data-center-campus-planned-outside-atlanta-georgia/

Historical reported substation count · 2 substations

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32187 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Gigawatt-scale data center campus planned outside Atlanta, Georgia

    Data Center Dynamics · Document date: Jul 27, 2026 · Primary

    Source reference: SRC-1821 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/gigawatt-scale-data-center-campus-planned-outside-atlanta-georgia/

Historical potential investment · $13 billion

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32188 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Gigawatt-scale data center campus planned outside Atlanta, Georgia

    Data Center Dynamics · Document date: Jul 27, 2026 · Primary

    Source reference: SRC-1821 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/gigawatt-scale-data-center-campus-planned-outside-atlanta-georgia/

Historical estimated completion · 2031-12-31

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32189 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. DRI Initial Information Form #4794 — Stillwater Technology Park

    Georgia Department of Community Affairs · Document date: Not stated · Primary

    Source reference: SRC-1819 · Recorded authority: Official primary

    Source URL

    https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4794

Proposal withdrawn · True

Actual · Stillwater Technology Park — Lovejoy (Project)

Claim 32190 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Proposal for Clayton County data center withdrawn

    Atlanta News First · Document date: Aug 7, 2026 · Primary

    Source reference: SRC-1822 · News report · Recorded authority: Secondary

    Source URL

    https://www.cbs46.com/2026/08/07/proposal-clayton-county-data-center-withdrawn/

Counterparties and capital

Central Georgia EMC · Utility provider · CMP-0889

City of Lovejoy · Government authority · CMP-0887

Clayton County · Government authority · CMP-0890

Georgia Department of Community Affairs · Government authority · CMP-0888

Henry County · Government authority · CMP-0891

Stillwater Development LLC · Developer · CMP-0886

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.