Stillwater Technology Park — Lovejoy
- Utility capacity
- 1,250 MW
- Updated
- Oct 28, 2026
- Utility
- Central Georgia EMC
On September 21, 2026, Lovejoy adopted an immediately effective citywide prohibition on data centers. This is subsequent regulatory context for the already withdrawn Stillwater proposal, not a second cancellation event or a revival of its historical capacity plans. A withdrawn proposal at Panhandle Road. Historical service and development envelopes. Stillwater Technology Park — Lovejoy is located in Lovejoy, GA, US and is a data center campus in cancelled status.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Milestones (3)
Dec 15, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedJul 22, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedAug 6, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Proposal for Clayton County data center withdrawn · Aug 7, 2026 · Corroborating
Developer (1)
Other participants (5)
Utility provider
Sources by role
Utility provider (1)
- Gigawatt-scale data center campus planned outside Atlanta, Georgia · Jul 27, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Proposal for Clayton County data center withdrawn · Aug 7, 2026 · Corroborating
Government authority (1)
- City Council Agenda — December 15, 2025 · Dec 15, 2025 · Primary
Government authority
Sources by role
Government authority (1)
- Proposal for Clayton County data center withdrawn · Aug 7, 2026 · Corroborating
Government authority (1)
- City Council Agenda — December 15, 2025 · Dec 15, 2025 · Primary
Capital & incentives
Capital claims
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Cancelled or not proceeding
1.25 GW
Historical requested service/grid connection; not IT load and no longer an active project.
Cancelled or not proceeding
2 substations
Historical reported substation count; no executed interconnection verified.
Project map
Permit · Status not stated
0, 11760 and 11762 Panhandle Road
City of Lovejoy
Dec 15, 2025
Sources (2)
- Proposal for Clayton County data center withdrawn · Aug 7, 2026 · Corroborating
- City Council Agenda — December 15, 2025 · Dec 15, 2025 · Primary
Permit · Status not stated
Stillwater Technology Park
Georgia Department of Community Affairs
Jul 22, 2026
Sources (2)
- Proposal for Clayton County data center withdrawn · Aug 7, 2026 · Corroborating
- DRI Initial Information Form #4794 — Stillwater Technology Park · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.