Data center siteSite record

Start Campus SINES Data Campus

Sines, 15, PortugalOperating / Stabilized
Capacity
1,200 MW
Planned / design
Lead participant
Start Campus S.A.
Developer · Operator
Last updated
Aug 25, 2026
Most recent public record update

About Start Campus SINES Data Campus

SIN01 is operational and currently marketed at 37.5 MW. SIN02 is the next planned 200 MW facility, with Nscale targeting 66,000+ Rubin GPUs from late 2027. SIN03-06 remain future envelopes within the 1.2 GW campus. Participants include Start Campus S.A. as developer, Start Campus S.A. as operator, Davidson Kempner Capital Management as owner, Pioneer Point Partners as owner. Published specifications include 1200 MW planned capacity, 37.5 MW operating it capacity, 200 MW planned capacity. Development comprises SIN01 (operational), SIN02 (development), SIN03 (planned). Key milestones include SIN01 officially inaugurated. (2025-04-04) and Start Campus and EDP signed renewable-energy framework. (2026-02-25). electric grid allocation — 1200 MW: Secured IT power allocation for full campus buildout; building energization sequence remains open. power transformers: More than EUR20m transformer order supporting campus expansion; unit count and ratings not public.

Program relationships

0 linked

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential1,200 MWActual · Start Campus SINES Data Campus
It Load37.5 MWActual · Start Campus SINES Data Campus
Future Potential200 MWActual · Start Campus SINES Data Campus

Development

6 phases · 4 milestones
SIN01Operational

First operating campus building; dated capacity figures evolved from 14 to 26 to 31 to current 37.5 MW.

1 building

SIN02Announced Or Preconstruction

Next building; dated design evolved from 180 MW to current 200 MW.

1 building

SIN03Planned

One of four future buildings within the 1.2 GW campus envelope; no current building-specific capacity should be inferred.

1 building

SIN04Planned

One of four future buildings within the 1.2 GW campus envelope; no current building-specific capacity should be inferred.

1 building

SIN05Planned

One of four future buildings within the 1.2 GW campus envelope; no current building-specific capacity should be inferred.

1 building

SIN06Planned

One of four future buildings within the 1.2 GW campus envelope; no current building-specific capacity should be inferred.

1 building

Aug 8, 2024
REN allocation increased campus envelope to 1.2 GW
Completed
Oct 1, 2024
SIN01 began operations
Completed
Apr 4, 2025
SIN01 officially inaugurated
Completed
Feb 25, 2026
Start Campus and EDP signed renewable-energy framework
Completed

Infrastructure

Electric GridSecured Or Contracted

1,200 MW

Secured IT power allocation for full campus buildout; building energization sequence remains open.

Electric GridSecured Or Contracted

More than EUR20m transformer order supporting campus expansion; unit count and ratings not public.

Renewable Energy SupplySecured Or Contracted

Non-binding preferred-partner framework; no contracted MWh or PPA term asserted.

FiberReported Context

DE-CIX interconnection is marketed at the campus.

Project map

0 of 1 project point mapped
Infrastructure facts
4
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 3Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

10 facts
Campus Planned It Capacity
1,200 MW
Actual
Planned Building Count
6
Actual
Sin01 Current Marketed Capacity
37.5 MW
Actual
Sin01 Operational
True
Fact
Sin02 Current Planned Capacity
200 MW
Actual
Expected Construction Investment
€8.50 billion
Actual
Target Pue
1.1 ratio
Actual
Target Wue
0 litres per kWh
Actual
Renewable Energy Claim
100 percent
Actual
Sin01 Privately Funded Without Public Subsidy
True
Fact