STACK SVY02 Santa Clara Data Center Campus

PRJ-0903 · Site · Santa Clara, California, United States

Record last updated Oct 28, 2026

Scope and capacity

STACK SVY02 Santa Clara Data Center Campus, also known as STACK SVY02, is a data center project in Santa Clara, CA, US developed and operated by STACK Infrastructure. Nine-acre, single-building Silicon Valley campus with 48 MW of flexible critical capacity and 560,440 square feet. Dedicated onsite substation and contracted utility capacity in the supply-constrained Santa Clara market.

Headline: 48 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · STACK SVY02 | Santa Clara | CA | US

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 64184 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Lifecycle status · Partially operational

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 64185 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Reported capacity · 48 MW

Design · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 64186 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Capacity basis · STACK Infrastructure publishes 48 MW of critical IT capacity for this record boundary.

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 64187 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Location context · STACK SVY02 | Santa Clara | CA | US

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93360 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Lifecycle status · Partially operational

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93361 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Reported capacity · 48 MW

Planned / design or future potential · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93362 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Capacity basis · 48 MW facility or campus design capacity.

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93363 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Site area · 9 acres

Actual · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93364 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK Infrastructure STACK SVY02 profile

    STACK Infrastructure · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3605 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/silicon-valley/svy02/

Building area · 560,440 square feet

Design · STACK SVY02 Santa Clara Data Center Campus (Project)

Claim 93365 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. STACK Americas current portfolio

    STACK Infrastructure · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-5182 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/locations/americas/

Counterparties and capital

STACK Infrastructure · Developer · CMP-0102

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.