Cartis diligence evidence schedule
STACK MIL05 Milan Data Center Campus
PRJ-0920 · Site · Milan, Lombardy, Italy
Record last updated Oct 28, 2026
Scope and capacity
STACK MIL05 is a two-building, 60 MW future campus at Vignate east of Milan. The Italian environment ministry completed procedure 13497 and issued positive decree DM_2026-0000411 with prescriptions on 30 June 2026. The approval advances the regulatory record but does not prove construction start, energization or operating IT. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.
Headline: 60 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (18)
Location context · STACK MIL05 | Milan | Lombardy | IT
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 64927 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Lifecycle status · Preconstruction
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 64928 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Reported capacity · 60 MW
Design · STACK MIL05 Milan Data Center Campus (Project)
Claim 64929 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Capacity basis · STACK Infrastructure publishes 60 MW of critical IT capacity for this record boundary.
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 64930 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Location context · STACK MIL05 | Milan | Lombardy | IT
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88642 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Lifecycle status · Preconstruction
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88643 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Reported capacity · 60 MW
Planned / design or future potential · STACK MIL05 Milan Data Center Campus (Project)
Claim 88644 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Capacity basis · 60 MW is the published future facility or full build design boundary;
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88645 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Operator or developer · STACK Infrastructure
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88646 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Project location · Milan, Lombardy, IT
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88647 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Current lifecycle · Under development
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88648 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Capacity classification · Future potential
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88649 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Capacity basis · 60 MW is the published future facility or full build design boundary;
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88650 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Customer utilization · Not publicly disclosed
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88652 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Source refresh date · 2026-08-29
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88654 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Site area · 23 acres
Design · STACK MIL05 Milan Data Center Campus (Project)
Claim 88655 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Building count · 2 buildings
Design · STACK MIL05 Milan Data Center Campus (Project)
Claim 88656 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- STACK Infrastructure STACK MIL05 profile
STACK Infrastructure · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3650 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.stackinfra.com/locations/emea/milan/mil05/
https://www.stackinfra.com/locations/emea/milan/mil05/
Via decree · DM 2026-0000411
Actual · STACK MIL05 Milan Data Center Campus (Project)
Claim 88657 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- MIL05 environmental-impact procedure 13497
Italian Ministry of Environment and Energy Security · Document date: Jun 30, 2026 · Primary
Source reference: SRC-4887 · Government record · Recorded authority: Official primary
Source URL
https://va.mite.gov.it/it-IT/Oggetti/Info/11494
https://va.mite.gov.it/it-IT/Oggetti/Info/11494
Counterparties and capital
STACK Infrastructure · Developer · CMP-0102
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.