Cartis diligence evidence schedule
Soluna Project Hedy AI Data Center Campus
PRJ-0731 · Site · Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Soluna has designated Project Hedy for AI and HPC development with a 198 MW behind-the-meter power term sheet. The record remains early-stage pending site and customer milestones. Soluna Holdings is publicly identified in the project record for Texas location undisclosed, TX, US. The disclosed development record includes 198 MW behind-the-meter power term sheet; dedicated to AI and HPC development. Power and infrastructure include proposed behind-the-meter renewable-energy data-center development. Soluna reports 198 MW of behind-the-meter power under a project term sheet. The available evidence does not establish a project-scoped operating or contracted capacity figure.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Location context · Project Hedy | Texas | precise boundary undisclosed
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 58771 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3223 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
Lifecycle status · Proposed
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 58772 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3223 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
Development scale · 198 MW behind the meter power term sheet
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 107604 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna Q2 2026 business update
Soluna Holdings · Document date: Aug 13, 2026 · Corroborating
Source reference: SRC-6013 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.solunacomputing.com/investors/updates/q2-2026-results/
https://www.solunacomputing.com/investors/updates/q2-2026-results/
Development milestone · Dedicated to AI and HPC development.
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 107605 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna Q2 2026 business update
Soluna Holdings · Document date: Aug 13, 2026 · Corroborating
Source reference: SRC-6013 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.solunacomputing.com/investors/updates/q2-2026-results/
https://www.solunacomputing.com/investors/updates/q2-2026-results/
Material uncertainty · The 198 MW value is a term sheet stage power figure, not secured operating capacity.
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 107606 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna Q2 2026 business update
Soluna Holdings · Document date: Aug 13, 2026 · Corroborating
Source reference: SRC-6013 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.solunacomputing.com/investors/updates/q2-2026-results/
https://www.solunacomputing.com/investors/updates/q2-2026-results/
Boundary context · Project Hedy | Texas | precise boundary undisclosed
Actual · Soluna Project Hedy AI Data Center Campus (Project)
Claim 107607 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Soluna reports Q2 2026 results
Soluna Holdings · Document date: Aug 13, 2026 · Primary
Source reference: SRC-3220 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
https://www.sec.gov/Archives/edgar/data/64463/000149315226037734/ex99-1.htm
- Soluna Q2 2026 business update
Soluna Holdings · Document date: Aug 13, 2026 · Corroborating
Source reference: SRC-6013 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.solunacomputing.com/investors/updates/q2-2026-results/
https://www.solunacomputing.com/investors/updates/q2-2026-results/
Counterparties and capital
Soluna Holdings · Developer · CMP-1467
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.