Cartis diligence evidence schedule
Rowan Project Temple
PRJ-0503 · Site · Temple, Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Rowan is building a 300 MW hyperscale campus on roughly 700 acres in south Temple for an undisclosed global technology customer. Construction is underway, power is secured through Oncor, and operations are expected in 2027.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (3)
Water initial fill maximum · 2 million US gallons
Actual · Rowan Project Temple (Project)
Claim 131845 · Recorded claim type: Actual · Review: Approved · Claim date: Mar 6, 2026
- Temple City Council approves water service agreement for data center
KXXV 25 News · Document date: Mar 6, 2026 · Primary
Source reference: SRC-2581 · News report · Recorded authority: Secondary
Source URL
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
Water daily maximum · 4,000 US gallons/day
Actual · Rowan Project Temple (Project)
Claim 131846 · Recorded claim type: Actual · Review: Approved · Claim date: Mar 6, 2026
- Temple City Council approves water service agreement for data center
KXXV 25 News · Document date: Mar 6, 2026 · Primary
Source reference: SRC-2581 · News report · Recorded authority: Secondary
Source URL
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
Cooling system · Closed loop
Actual · Rowan Project Temple (Project)
Claim 131847 · Recorded claim type: Actual · Review: Approved · Claim date: Mar 6, 2026
- Temple City Council approves water service agreement for data center
KXXV 25 News · Document date: Mar 6, 2026 · Primary
Source reference: SRC-2581 · News report · Recorded authority: Secondary
Source URL
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
https://www.kxxv.com/news/local-news/in-your-neighborhood/bell-county/temple/temple-city-council-approves-water-service-agreement-for-data-center
Counterparties and capital
Bell Canada · Government authority · CMP-1179
Blackstone · Investor · CMP-0661
City of Temple · Government authority · CMP-1209
Quinbrook Infrastructure Partners · Investor · CMP-1210
Rowan Digital Infrastructure · Developer · CMP-1208
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.