Rowan Project Temple

Temple, Texas, United StatesUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Rowan is building a 300 MW hyperscale campus on roughly 700 acres in south Temple for an undisclosed global technology customer. Construction is underway, power is secured through Oncor, and operations are expected in 2027.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Flagship campus constructionUnder construction

300 MW full build-out; customer identity undisclosed.

Operations targetPlanned

Forecast, not achieved operations.

Milestones (4)
Temple City Council unanimously approved plans

Sep 18, 2025 · Recorded actual event

Completed · Permit approved

Source not linked
Construction started in late 2025

2025 · Recorded actual event

Completed · Construction started

Source not linked
Ceremonial groundbreaking held

Mar 2, 2026 · Recorded actual event

Completed · Construction started

Source not linked
Nearly $3bn debt financing announced

May 27, 2026 · Recorded actual event

Completed · Financing

Source not linked

Participants

Blackstone

Investor

Sources by role
Quinbrook Infrastructure Partners

Investor

Sources by role
Rowan Digital Infrastructure

Developer

Sources by role
Other participants (2)
Bell Canada

Government authority

Sources by role
City of Temple

Government authority

Sources by role
Government authority (1)

Technical specifications

Water initial fill maximum

Actual

2 million US gallons

Source

Water daily maximum

Actual

4,000 US gallons/day

Source

Cooling system

Actual

Closed loop

Source

Infrastructure & permits

Technical details (5)
Electric grid

Under construction

300 MW

Full-build campus design scale.

Electric grid

Secured or contracted

300 MW

Power secured through Oncor; capacity label follows campus scale, not observed load.

Electric grid

Reported context

Existing Moriah utility and Rowan power infrastructure avoids new transmission/substation construction.

Water supply

Secured or contracted

2 million US gallons

Reported agreement range is 1–2 million gallons; maximum retained.

Water supply

Secured or contracted

4,000 US gallons/day

Closed-loop cooling daily maximum after initial fill.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (2)
Rowan Project Ranger

Preconstruction · Temple, Texas, United States

Same locality: Temple · Shared participant: City of Temple · Shared participant: Rowan Digital Infrastructure

Compare in a collection
Rowan Moriah Data Center

Cancelled · Temple, Texas, United States

Same locality: Temple

Compare in a collection