QTS SUW1 Suwanee Data Center Campus

Suwanee, Georgia, United StatesPartially operational
Capacity
50 MW
Planned / design
Lead participant
QTS Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About QTS SUW1 Suwanee Data Center Campus

QTS SUW1 Suwanee Data Center Campus, also known as QTS Suwanee 1, is a partially operational data center campus in Suwanee, GA, US associated with QTS Data Centers. 53-acre QTS location; 50 MW+ published campus capacity.

Projects sharing a market, utility, or organization.

3 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load50 MWDesign · QTS SUW1 Suwanee Data Center Campus
Design50 MWDesign · QTS SUW1 Suwanee Data Center Campus
Design50 MWDesign · QTS SUW1 Suwanee Data Center Campus

Development

2 phases · 3 milestones
Operating facility and documented expansionPartially Operational

50 MW is the operator-published facility or campus design boundary. It is not measured tenant utilization or live IT draw.

Operating facility and documented expansionPartially Operational

50 MW is the operator-published facility or campus IT design boundary. It is not measured tenant utilization or live IT draw.

Aug 27, 2026
Primary project source reviewed for QTS Suwanee 1
Completed
Aug 28, 2026
Current source record reviewed for QTS Suwanee 1
Completed
Aug 30, 2026
Design capacity reviewed without inferring tenant utilization
Completed

Infrastructure

Electric GridEnergized

Atlanta-region infrastructure with scalable power, diverse connectivity, redundant cooling and multilayer security.

FiberEnergized

QTS campus conduit and carrier access are documented in current portfolio and compliance materials.

Electric GridEnergized

QTS campus designed and operated for large-scale data center deployments; project-specific utility details require separate sourcing.

Cooling SystemOperational

Cooling and efficiency claims remain limited to source-defined designs; no delivered load or water use is inferred.

Onsite GenerationPermitted Or Installed

Georgia EPD permit covers emergency generators; engine ratings are not IT capacity.

Project map

0 of 1 project point mapped
Infrastructure facts
5
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2Generation & storage: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

20 facts
Location Context
QTS Suwanee 1 | Suwanee | GA | US
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
50 MW
Design
Capacity Basis
QTS Data Centers publishes 50 MW of critical IT capacity for this record boundary.
Actual
Location Context
QTS Suwanee 1 | Suwanee | GA | US
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
50 MW
Design
Capacity Basis
50 MW facility or campus design capacity.
Actual
Project Boundary
QTS Suwanee 1
Actual
Location Context
Suwanee, GA, US
Actual
Lifecycle Status
Partially operational
Actual
Capacity Basis
50 MW facility or campus design capacity.
Actual
Location Context
QTS Suwanee 1 location | Suwanee | GA | United States
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
50 MW
Design
Capacity Basis
50 MW facility or campus IT design capacity.
Actual
Current Critical Design
50+ MW
Design
Future Marketed Potential
100+ MW
Forecast
Site Area
53 acres
Actual
Address
300 Satellite Boulevard
Actual