Cartis diligence evidence schedule
QTS–Lancium Hall County Campus
PRJ-0258 · Site · Turkey, Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
In an October 9, 2026 release, QTS and Lancium announced an agreement supporting Turkey's infrastructure and community priorities and described Hall County campus construction as progressing. The agreement provides up to $15.5 million in municipal support, not the campus construction budget; it does not establish a precise construction start, building-phase completion or opening date. QTS–Lancium Hall County Campus — Lancium-owned Clean Campus near Turkey with QTS-designed, built and operated data-center buildings; separate from Lancium Abilene, Lancium Childress and IREN Childress.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Planned building count · 11 buildings
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24904 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- Texas governor orders pause on new data center approvals pending audit
Reuters · Document date: Aug 4, 2026 · Corroborating
Source reference: SRC-1389 · News report · Recorded authority: Secondary
Source URL
https://www.reuters.com/business/energy/texas-governor-orders-pause-new-data-center-approvals-pending-audit-2026-08-04/
https://www.reuters.com/business/energy/texas-governor-orders-pause-new-data-center-approvals-pending-audit-2026-08-04/
- QTS to build 11 data centers on Lancium campus in Hall County
Data Center Dynamics · Document date: Jul 15, 2026 · Corroborating
Source reference: SRC-1387 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/qts-to-build-11-data-centers-on-lancium-campus-in-hall-county-texas/
https://www.datacenterdynamics.com/en/news/qts-to-build-11-data-centers-on-lancium-campus-in-hall-county-texas/
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
- Hall County approves abatements for Lancium Clean Campus
Caprock Courier · Document date: Jun 11, 2025 · Corroborating
Source reference: SRC-1386 · News report · Recorded authority: Secondary
Source URL
https://www.caprockcourier.com/news/hall-county-approves-abatements-lancium-clean-campus-construction-data-center-begin-2026-south
https://www.caprockcourier.com/news/hall-county-approves-abatements-lancium-clean-campus-construction-data-center-begin-2026-south
- Commissioners Court Agenda — June 9, 2025
Hall County Commissioners Court · Document date: Jun 9, 2025 · Corroborating
Source reference: SRC-1385 · Government record · Recorded authority: Official primary
Source URL
https://www.co.hall.tx.us/upload/page/9510/2025/CCE_000213.pdf
https://www.co.hall.tx.us/upload/page/9510/2025/CCE_000213.pdf
- Regular Minutes — May 12, 2025
Hall County Commissioners Court · Document date: May 12, 2025 · Corroborating
Source reference: SRC-1384 · Government record · Recorded authority: Official primary
Source URL
https://www.co.hall.tx.us/upload/page/9510/REG%20MIN%205-12-2025.pdf
https://www.co.hall.tx.us/upload/page/9510/REG%20MIN%205-12-2025.pdf
Site area · 465 acres
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24905 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Investment · $10 billion
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24906 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Construction jobs peak · 7,000 jobs
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24907 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Construction jobs peak · 6,000 jobs
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24908 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Permanent jobs · 350 jobs
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24909 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 13, 2026
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Energy infrastructure cost allocation · 100% Developer funded
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24911 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Cooling design · Closed loop; no ongoing cooling water consumption after charge
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24912 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
- Hall County, Texas
QTS · Document date: Jul 13, 2026 · Corroborating
Source reference: SRC-1383 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/data-centers/hall-county/
https://q.com/data-centers/hall-county/
Water source · Onsite wells or approved external sources; not Turkey municipal system
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24913 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- QTS and Lancium Announce Data Center Campus in Hall County, Texas
Lancium · Document date: Jul 13, 2026 · Primary
Source reference: SRC-1382 · Company announcement · Recorded authority: Party primary
Source URL
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
https://lancium.com/2026/07/13/qts-and-lancium-announce-data-center-campus-in-hall-county-texas/
Abatement agreement scope · $20 billion
Source report · QTS–Lancium Hall County Campus (Project)
Claim 24915 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Commissioners Court Agenda — June 9, 2025
Hall County Commissioners Court · Document date: Jun 9, 2025 · Primary
Source reference: SRC-1385 · Government record · Recorded authority: Official primary
Source URL
https://www.co.hall.tx.us/upload/page/9510/2025/CCE_000213.pdf
https://www.co.hall.tx.us/upload/page/9510/2025/CCE_000213.pdf
Counterparties and capital
City of Turkey, Texas · Government authority · CMP-0694
Electric Reliability Council of Texas · Utility provider · CMP-0366
Hall County, Texas · Government authority · CMP-0693
Lancium · Owner · CMP-0004
Public Utility Commission of Texas · Government authority · CMP-0695
QTS Data Centers · Developer, Operator · CMP-0368
Texas Commission on Environmental Quality · Government authority · CMP-0020
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.