Skip to content
← Return to profile

Cartis diligence evidence schedule

QTS GRO Groningen Data Center

PRJ-0941 · Site · Groningen, Netherlands

Captured 2026-09-06T04:12:54.463Z · Record last updated 2026-08-28

SHA-256: 90bdaa733892d898a89fef44ae42fa77f2112ae058ade5c9325769ce5f7ec58b

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

QTS Groningen is the existing operating Groningen facility and remains part of QTS after the Zentrys acquisition. Its 4 MW published facility boundary is distinct from the larger Eemshaven development program. The 2019 acquisition price covered two Dutch sites and is recorded only as shared transaction context. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Headline: 4 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · QTS Groningen | Groningen | Groningen | NL

actual · QTS GRO Groningen Data Center (project)

Claim 65011 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Lifecycle Status · Partially operational

actual · QTS GRO Groningen Data Center (project)

Claim 65012 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Reported Capacity · 4 MW

design · QTS GRO Groningen Data Center (project)

Claim 65013 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Capacity Basis · QTS Data Centers publishes 4 MW of critical IT capacity for this record boundary.

actual · QTS GRO Groningen Data Center (project)

Claim 65014 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Location Context · QTS Groningen | Groningen | Groningen | NL

actual · QTS GRO Groningen Data Center (project)

Claim 88950 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Lifecycle Status · Partially operational

actual · QTS GRO Groningen Data Center (project)

Claim 88951 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Reported Capacity · 4 MW

Planned / design or future potential · QTS GRO Groningen Data Center (project)

Claim 88952 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Capacity Basis · 4 MW is the operator published facility design or maximum power boundary; it is not measured tenant utilization.

Facility electrical / design capacity · QTS GRO Groningen Data Center (project)

Claim 88953 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Operator Or Developer · QTS Data Centers

actual · QTS GRO Groningen Data Center (project)

Claim 88954 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Project Location · Groningen, Groningen, NL

actual · QTS GRO Groningen Data Center (project)

Claim 88955 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Current Lifecycle · Operating or in phased operation

actual · QTS GRO Groningen Data Center (project)

Claim 88956 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Capacity Classification · Design

actual · QTS GRO Groningen Data Center (project)

Claim 88957 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Capacity Basis · 4 MW is the operator published facility design or maximum power boundary; it is not measured tenant utilization.

Facility electrical / design capacity · QTS GRO Groningen Data Center (project)

Claim 88958 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Customer Utilization · Not publicly disclosed

actual · QTS GRO Groningen Data Center (project)

Claim 88960 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Source Refresh Date · 2026-08-29

actual · QTS GRO Groningen Data Center (project)

Claim 88962 · Review: Approved · Claim date: Not published

  1. QTS data center portfolio — Groningen

    QTS Data Centers · Document date: 2026-08-28 · Primary

    https://qtsdatacenters.com/data-centers/

Current Portfolio Presence · Confirmed in QTS current portfolio

actual · QTS GRO Groningen Data Center (project)

Claim 88963 · Review: Approved · Claim date: Not published

  1. QTS acquisition of Zentrys

    QTS Data Centers · Document date: 2023-11-07 · Primary

    https://q.com/news/qts-acquires-netherlands-based-data-center-management-company-zentrys/

Facility Compliance Scope · Current QTS compliance matrix reviewed

actual · QTS GRO Groningen Data Center (project)

Claim 88964 · Review: Approved · Claim date: Not published

  1. QTS acquisition of Eemshaven and Groningen facilities

    Groningen Seaports · Document date: 2019-04-30 · Primary

    https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/

Shared Acquisition Assets · 2 facilities

transaction scope · QTS GRO Groningen Data Center (project)

Claim 88965 · Review: Approved · Claim date: Not published

  1. QTS acquisition of Eemshaven and Groningen facilities

    Groningen Seaports · Document date: 2019-04-30 · Primary

    https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/

Shared Acquisition Price · $44,000,000

transaction scope · QTS GRO Groningen Data Center (project)

Claim 88966 · Review: Approved · Claim date: Not published

  1. QTS acquisition of Eemshaven and Groningen facilities

    Groningen Seaports · Document date: 2019-04-30 · Primary

    https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/

Counterparties and capital

QTS Data Centers · Developer · CMP-0368

Equity Investment

$44,000,000 · 2019-04-30

Combined Groningen and Eemshaven acquisition price; not a standalone GRO valuation.

QTS Data Centers (Borrower)

Financing record 182; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.