Cartis diligence evidence schedule
QTS EEM Netherlands–Eemshaven Data Center
PRJ-0929 · Site · Eemshaven, Groningen, Netherlands
Record last updated Oct 28, 2026
Scope and capacity
QTS’s current Eemshaven page identifies DC1 as fully operational, DC2 as being delivered in phases, and DC3 as under construction. The 200 MW campus figure is planned gross power delivered in phases, not operating IT capacity. QTS Eemshaven remains an operating Netherlands facility and is still in QTS’s portfolio following the 2023 acquisition of local operator Zentrys. The legacy 20 MW boundary is kept separate from later hyperscale expansion: Groningen province issued a current permit at Kwelderweg, but that decision does not prove the existing building’s operating IT changed. The 2019 $44 million purchase price covered both Eemshaven and Groningen and is not allocated to this profile. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.
Headline: 20 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (19)
Location context · QTS Netherlands–Eemshaven | Eemshaven | Groningen | NL
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 64963 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Lifecycle status · Partially operational
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 64964 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Reported capacity · 20 MW
Design · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 64965 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Capacity basis · QTS Data Centers publishes 20 MW of critical IT capacity for this record boundary.
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 64966 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Location context · QTS Netherlands–Eemshaven | Eemshaven | Groningen | NL
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88773 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Lifecycle status · Partially operational
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88774 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Reported capacity · 20 MW
Planned / design or future potential · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88775 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Capacity basis · 20 MW is the operator published facility design or maximum power boundary; it is not measured tenant utilization.
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88776 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Operator or developer · QTS Data Centers
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88777 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Project location · Eemshaven, Groningen, NL
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88778 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Current lifecycle · Operating or in phased operation
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88779 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Capacity classification · Design
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88780 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Capacity basis · 20 MW is the operator published facility design or maximum power boundary; it is not measured tenant utilization.
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88781 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Customer utilization · Not publicly disclosed
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88783 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Source refresh date · 2026-08-29
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88785 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS data center portfolio — Netherlands–Eemshaven
QTS Data Centers · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3661 · Fact sheet · Recorded authority: Official primary
Source URL
https://qtsdatacenters.com/data-centers/
https://qtsdatacenters.com/data-centers/
Current portfolio presence · Confirmed in QTS current portfolio
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88786 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS acquisition of Zentrys
QTS Data Centers · Document date: Nov 7, 2023 · Primary
Source reference: SRC-4905 · Company announcement · Recorded authority: Party primary
Source URL
https://q.com/news/qts-acquires-netherlands-based-data-center-management-company-zentrys/
https://q.com/news/qts-acquires-netherlands-based-data-center-management-company-zentrys/
Facility compliance scope · Current QTS compliance matrix reviewed
Actual · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88787 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- QTS Eemshaven environmental permit decision
Province of Groningen · Document date: Jan 30, 2026 · Primary
Source reference: SRC-4906 · Government record · Recorded authority: Official primary
Source URL
https://www.provinciegroningen.nl/vergunningen/verleende-vergunningen-bedrijven/bedrijf/quality-technology-service-qts-kwelderweg-te-eemshaven/
https://www.provinciegroningen.nl/vergunningen/verleende-vergunningen-bedrijven/bedrijf/quality-technology-service-qts-kwelderweg-te-eemshaven/
Two asset acquisition price · $44,000,000
Transaction scope · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88788 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Not stated
- QTS acquisition of Eemshaven and Groningen facilities
Groningen Seaports · Document date: Apr 30, 2019 · Primary
Source reference: SRC-4907 · Company announcement · Recorded authority: Party primary
Source URL
https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/
https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/
Anticipated recommissioning capex · $15,000,000
Transaction scope · QTS EEM Netherlands–Eemshaven Data Center (Project)
Claim 88789 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Not stated
- QTS acquisition of Eemshaven and Groningen facilities
Groningen Seaports · Document date: Apr 30, 2019 · Primary
Source reference: SRC-4907 · Company announcement · Recorded authority: Party primary
Source URL
https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/
https://www.groningen-seaports.com/en/nieuws/qts-expands-international-platform-with-the-strategic-acquisition-of-two-data-centers-in-eemshaven-and-groningen/
Counterparties and capital
QTS Data Centers · Developer · CMP-0368
$44,000,000 · Apr 30, 2019
Combined Eemshaven and Groningen acquisition price including closing costs; not a standalone EEM facility valuation.
QTS Data Centers (Borrower)
Sources (1)
- QTS acquisition of Eemshaven and Groningen facilities · Apr 30, 2019
Financing record 181; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.