Cartis diligence evidence schedule
Pure DC Dublin Ballycoolin Campus
PRJ-0507 · Site · Ballycoolin, Dublin 15, Ireland
Record last updated Oct 28, 2026
Scope and capacity
A June 2026 Ingeteam supplier announcement reproduced by IDRA reports that the Orion Phase 1 battery system at Pure DC’s Dublin campus was commissioned and operating, with 10 MW of power and 20 MWh of storage. This initial battery installation does not establish commissioning of the entire planned 110 MW permanent microgrid. Pure DC's Ballycoolin campus has operated since 2024 and is designed for 54 MW across three data-centre buildings. The first is live, later buildings are permitted, and an onsite microgrid supports phased delivery.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (1)
Project identity · Pure DC Dublin Ballycoolin Campus
Source report · Pure DC Dublin Ballycoolin Campus (Project)
Claim 132363 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Dublin (Ballycoolin)
Pure Data Centres Group · Document date: Not stated · Primary
Source reference: SRC-6998 · Fact sheet · Recorded authority: Party primary
Source URL
https://puredc.com/dublin
https://puredc.com/dublin
- Pure DC and AVK Deploy Europe’s First Data Centre Microgrid
Pure Data Centres Group · Document date: Mar 11, 2026 · Primary
Source reference: SRC-7000 · Company announcement · Recorded authority: Party primary
Source URL
https://puredc.com/2026/03/11/pure-dc-and-avk-deploy-europes-first-data-centre-microgrid
https://puredc.com/2026/03/11/pure-dc-and-avk-deploy-europes-first-data-centre-microgrid
Counterparties and capital
ABN AMRO · Lender · CMP-0398
Allianz Global Investors · Lender · CMP-1165
EirGrid · Utility provider · CMP-0721
Fingal County Council · Government authority · CMP-1215
SMBC · Lender · CMP-0667
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.