Pure DC Dublin Ballycoolin Campus

Ballycoolin, Dublin 15, IrelandPartially operational
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026
Utility
EirGrid

A June 2026 Ingeteam supplier announcement reproduced by IDRA reports that the Orion Phase 1 battery system at Pure DC’s Dublin campus was commissioned and operating, with 10 MW of power and 20 MWh of storage. This initial battery installation does not establish commissioning of the entire planned 110 MW permanent microgrid. Pure DC's Ballycoolin campus has operated since 2024 and is designed for 54 MW across three data-centre buildings. The first is live, later buildings are permitted, and an onsite microgrid supports phased delivery.

Constituent sites / phases

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Permitted three-building campusOperational

3 buildings

54 MW total across operator-named buildings.

Milestones (1)
$2.7bn combined financing announced

May 27, 2026 · Recorded actual event

Completed · Financing

Source not linked

Participants

Other participants (5)
ABN AMRO

Lender

Sources by role
Allianz Global Investors

Lender

Sources by role
EirGrid

Utility provider

Sources by role
Fingal County Council

Government authority

Sources by role
SMBC

Lender

Sources by role

Additional project facts

Project identity

Source report

Pure DC Dublin Ballycoolin Campus

Source

Infrastructure & permits

Technical details (1)
Natural gas pipeline

Reported context

200 MW thermal

Fuel-input connection, not electrical output or IT capacity.

Public-source research. Plans may change. See Evidence for sources and qualifications.