Cartis diligence evidence schedule

Pure DC Amsterdam Westpoort AMS01

PRJ-0279 · Site · Amsterdam Westpoort, NH, Netherlands

Captured 2026-09-06T04:13:58.526Z · Record last updated 2026-08-25

SHA-256: a327fddda1ffdaaf04471e9960fb74c840d6baca081962cf660e568e8e042ea3

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

The substation is operational and data-hall construction is underway. The 78 MW campus is fully leased, with phased delivery anticipated from 2028. Pure DC Amsterdam Westpoort AMS01 is in Amsterdam Westpoort, NH, NL and is a data center campus with under construction status.

Headline: 78 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Planned It Capacity · 78 MW

Planned / design or future potential · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26139 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. Pure DC secures additional EUR1.3 billion

    Pure DC · Document date: 2026-07-21 · Corroborating

    https://puredc.com/2026/07/21/pure-dc-secures-additional-e1-3-billion-to-accelerate-growth-of-one-of-europes-largest-ai-campuses
  2. Pure DC secures hyperscale customer for Amsterdam campus

    Data Center Dynamics · Document date: 2025-12-16 · Corroborating

    https://www.datacenterdynamics.com/en/news/pure-dc-secures-hyperscale-customer-for-78mw-data-center-campus-in-netherlands/
  3. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Corroborating

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  4. Oaktree-backed firm unveils Amsterdam data centre project

    Reuters · Document date: 2025-12-15 · Corroborating

    https://www.reuters.com/business/oaktree-backed-firm-unveils-12-billion-amsterdam-data-centre-project-2025-12-15/
  5. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Planned Building Count · 3 towers

Planned / design or future potential · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26140 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Corroborating

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  2. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Per Tower It Capacity · 26 MW

Planned / design or future potential · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26141 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Corroborating

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  2. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Utility Service Capacity · 100 MVA

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26142 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Primary

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits

Grid Connection Voltage · 50 kV

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26143 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Primary

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits

Private Substation Operational · True

Source report · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26144 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Corroborating

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  2. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Fully Leased · True

Source report · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26145 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Primary

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  2. Oaktree-backed firm unveils Amsterdam data centre project

    Reuters · Document date: 2025-12-15 · Corroborating

    https://www.reuters.com/business/oaktree-backed-firm-unveils-12-billion-amsterdam-data-centre-project-2025-12-15/

Customer Disclosed · False

Source report · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26146 · Review: Approved · Claim date: Not published

  1. Pure Data Centres launches new Amsterdam data centre fully leased with power and permits

    Pure DC · Document date: 2025-12-15 · Primary

    https://puredc.com/2025/12/15/pure-data-centres-launches-new-amsterdam-data-centre-fully-leased-with-power-and-permits
  2. Oaktree-backed firm unveils Amsterdam data centre project

    Reuters · Document date: 2025-12-15 · Corroborating

    https://www.reuters.com/business/oaktree-backed-firm-unveils-12-billion-amsterdam-data-centre-project-2025-12-15/

Planned Floor Area · 94,660 square metres

Planned / design or future potential · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26147 · Review: Approved · Claim date: Not published

  1. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Site Area · 5.68 acres

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26148 · Review: Approved · Claim date: Not published

  1. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Tower Height · 85 metres

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26149 · Review: Approved · Claim date: Not published

  1. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Target Pue · 1.2 ratio

Planned / design or future potential · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26150 · Review: Approved · Claim date: Not published

  1. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Expected Investment · €1 billion

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26151 · Review: Approved · Claim date: Not published

  1. Oaktree-backed firm unveils Amsterdam data centre project

    Reuters · Document date: 2025-12-15 · Corroborating

    https://www.reuters.com/business/oaktree-backed-firm-unveils-12-billion-amsterdam-data-centre-project-2025-12-15/
  2. Amsterdam Westpoort AMS01

    Pure DC · Document date: Not published · Primary

    https://puredc.com/amsterdam

Phased Delivery From Year · 2028

actual · Pure DC Amsterdam Westpoort AMS01 (project)

Claim 26152 · Review: Approved · Claim date: Not published

  1. Oaktree-backed firm unveils Amsterdam data centre project

    Reuters · Document date: 2025-12-15 · Primary

    https://www.reuters.com/business/oaktree-backed-firm-unveils-12-billion-amsterdam-data-centre-project-2025-12-15/

Counterparties and capital

Brookfield Asset Management · Owner · CMP-0743

Oaktree Capital Management · Owner · CMP-0742

Port of Amsterdam · Government Authority · CMP-0744

Pure Data Centres Group · Developer, Operator · CMP-0741

Long Leasehold Acquisition

Amount not disclosed · 2025-12-15

Long leasehold over 5.68-acre Amsterdam Westpoort site; consideration and term undisclosed.

Port of Amsterdam (Lessor) · Pure Data Centres Group (Lessee)

Financing record 70; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.